Site progress
On Building 1
The Unit 17,16,15,14 wall to floor connections is completed. The Unit 18, 16, 14 staircase is completed. However the Unit 17 and 15 staircase us still in progress. We have completed the rough- in plumbing layout for unit 18,17. as well as rough-in pipes for unit 18. demising densglass installation as well as passed the inspection for the same. The floor walls erection for Unit 17, Unit 16, Unit 15- 3rd floor has been completed.
We are currently working on the Unit 14 - 3rd floor walls erection as well as Unit 18 roof panels erection. We are estimating to start the roof panels erection on Unit 17 and Unit 16 next week.
The next task in our list for the next week is to start with the Unit 17,18,16,15,14 walls connection.
8. Demising Floor densglass installation - completed 9. U17,16,15,14 - Shear inspection - next week 10. U18 - Plumbing fixtures delivery - completed
Building 2:
On Unit 12& Unit 13 we are working on the floor panels erection. We will initiate the Unit 11& Unit 12 wall to wall and floor connection next week.
We are awaiting the Beams Delivery on Building 2 next week. As we receive it we will start the Beam installation and welding nest week.
Building-3:
We are working on Unit 9 Exterior & Interior wall panels erection. In addition, on Unit 8, Unit 7 and Unit 6 we are working on the demising wall erection
Building 1: 1. U17,16 wall to floor connections - completed 2. U15,14 wall to floor connections - completed 3. U18- staircase - completed 4. U16,14 - staircase - completed 5. U15.17 - staircase - in progress 6. U18,17- Rough-in plumbing layout - completed 7. U18 - Rough-in pipes - in progress 8. Demising Floor densglass installation - completed 9. U17,16,15,14 - Shear inspection - next week 10. U18 - Plumbing fixtures delivery - completed
Building-2: 1. U12,U13 floor panels erection - in progress 2. B2- beams delivery - this week 3. U10,11 Beam installation & welding - completed 4. U12,13 Beam installation & welding - in progress 5. Wall to wall connection U10 - completed 6. Wall to wall connection U11,12,13- next week
Building-3: 1. U9 - Ext&int wall panels erection - completed 2. U8,7,6 - demising wall erection - completed 3. Connections on hold
Building-4: The Rebar city inspection has been passed. We aim to start Concrete pour for slab this week- currently on hold due to rain
Finance: We are totally secured on financing and are working towards effective management of draws to keep the site funded and unblocked.
|