On Lot 1:
Exterior: All stucco patch and deck tiles were 100% completed.
On Lot 2:
Interior: All trades are finishing up, flooring is 90% complete. Electrical is 90% complete. Electric meter set inspection passed and we expect the meter to be set and house to have power next week. Dishwasher, Grabage disposal, Wine Refrigrator, oven, Microwave and the Refrigerator are installed.
Exterior: Siding installation is 100% complete, Staining is in progress. The deck tile is almost complete. Upstairs deck will be finished this weekend. Gutters are installed. Fascia board and gutters are painted 100%.