logo
logo
4 SFRs @ Aron Ct. (1320 Talbryn Dr. Belmont)
about
Overview

The investment involves the acquisition of four adjacent residential lots in Belmont, CA, then rebuild and sale of four single family homes. The Sponsor will acquire the necessary permits, rebuild, and sell the homes within 24 months.


As informed in the last update, we closed escrow on the last of the four homes at Aron Court. We will be sending out an email specifically to investors in this project regarding timelines going forward to completing the project and closing out this investment.


Screen shot 2021 01 11 at 7.08.28 pm Screen shot 2021 01 11 at 7.08.38 pm Screen shot 2021 01 11 at 7.08.49 pm Screen shot 2021 01 11 at 7.09.00 pm Screen shot 2021 01 11 at 7.09.10 pm

Yesterday, we closed escrow on the last of the four homes at Aron Court. There is a small holdback in for the last transaction pending punch list items to be completed prior to the full release of the complete purchase price. Our team is diligently working to complete those items as soon as possible. In the meantime, we will be working to finalize all accounting over the coming weeks and will stay in close communication with the individual investors.


Screen shot 2020 12 30 at 12.48.02 pm Screen shot 2020 12 30 at 12.48.10 pm Screen shot 2020 12 30 at 12.48.19 pm Screen shot 2020 12 30 at 12.48.30 pm

4 Aron Court is the last remaining house in the newly constructed cul-de-sac and is currently pending purchase as we work to complete the last remaining items.


Dsc03301 Dsc03318 Dsc03340 Dsc03346

We are working to close the last of the four homes at Aron Court. 4 Aron Court is pending with a list of punch list items to be completed before closing escrow. 


Screen shot 2020 12 11 at 6.09.38 pm Screen shot 2020 12 11 at 6.09.46 pm Screen shot 2020 12 11 at 6.09.56 pm Screen shot 2020 12 11 at 6.10.07 pm Screen shot 2020 12 11 at 6.10.17 pm Screen shot 2020 12 11 at 6.10.29 pm Screen shot 2020 12 11 at 6.10.44 pm Screen shot 2020 12 11 at 6.10.54 pm Screen shot 2020 12 11 at 6.11.03 pm Screen shot 2020 12 11 at 6.11.21 pm Screen shot 2020 12 11 at 6.12.17 pm Screen shot 2020 12 11 at 6.12.38 pm

Three of the four homes on Aron Court have sold. 4 Aron Court is in contract and we are working to try to close next week. We are also working to try to complete all remaining subdivision items for the cul-de-sac so we can officially close out all permits.


Screen shot 2020 12 05 at 5.41.57 pm Screen shot 2020 12 05 at 5.42.05 pm Screen shot 2020 12 05 at 5.42.14 pm Screen shot 2020 12 05 at 5.42.22 pm

As informed last week, we are in a non-contingent contract on 4 Aron Court and are working to complete a few items that the buyer has as a predecessor to closing escrow. Also, we are on track to close the Escrow next week & forward to closing this project.


Dsc03301 Dsc03311 Dsc03318 Dsc03346 Whatsapp image 2020 11 27 at 2.05.53 am

We are in a non-contingent contract on 4 Aron Court and are working to complete a few items that the buyer has as a predecessor to closing escrow. 4 Aron Court was the last of the four homes at Aron Court. We look forward to closing out this project and having four families move in and enjoy these amazing homes, with breathtaking views, on a beautiful new cul-de-sac.


Screen shot 2020 11 24 at 7.08.49 am

We have closed escrow on 2 Aron Court (Lot 4)

On 4 Aron Court, we are finishing the garage out in order to present better to potential buyers. We are also making some modifications to the upstairs living room as a result of feedback from a few different buyers. We were featured last week in the Mercury News and are investing in social media advertising. We are also working on the interior handrails and will be pushing towards receiving the occupancy certificate.


Dsc02561 Dsc03301 Dsc03311 Dsc03318 Dsc03327 Dsc03340 Dsc03346 Dsc03374

As announced last week, we are close to finalizing the escrow by mid-November on Lot 4. 

On Lot 3, we received an offer and countered. We are pushing across multiple marketing & listing platforms to draw good attention of buyers to the home. Most notably, we were featured in the Mercury News this morning. A preview of the article can be found here


Dsc02561 Dsc03301 Dsc03311 Dsc03318 Dsc03340 Dsc03346

We are on track to close escrow by mid November on Lot 4. We are working through several punch list items for the same and buyer's loan is approved as well. 

On lot 3, we received a non-contingent offer, however the price is significantly below our expectation. We have countered the offer and are in the process of negotiations. We are also exploring some low cost changes to the house to greatly enhance the appeal of the lot 3 house which we might incorporate if we are unable to negotiate successfully with the current offer at hand.


Dsc02561 Dsc03301 Dsc03311 Dsc03318 Dsc03327 Dsc03340 Dsc03346 Dsc03374

As announced last week, 2 Aron Court is in contract and we are moving forward to close escrow in the middle of November. 4 Aron Court has had multiple showings and the listing agent is currently going back and forth with multiple clients. We are pushing across multiple marketing platforms to draw as many eyes to the home as possible.


Screen shot 2020 10 23 at 4.31.58 pm Screen shot 2020 10 23 at 4.32.05 pm Screen shot 2020 10 23 at 4.32.13 pm Screen shot 2020 10 23 at 4.32.23 pm Screen shot 2020 10 23 at 4.32.34 pm Screen shot 2020 10 23 at 4.32.58 pm Screen shot 2020 10 23 at 4.33.06 pm Screen shot 2020 10 23 at 4.33.34 pm Screen shot 2020 10 23 at 4.34.00 pm Screen shot 2020 10 23 at 4.34.11 pm Screen shot 2020 10 23 at 4.34.28 pm

We are in a contingent contract to sell the third of the four homes. 2 Aron Court went into contract this past week. There were multiple showings over the last 7 days of 4 Aron Court and we are continuing to roll out a concentrated marketing effort to move the last of the homes. We are on track for a press release next week in the Mercury News and are also about to be featured on the newest episode (unedited sneak peak) on The American Dream series.


Screen shot 2020 10 16 at 1.42.46 pm Screen shot 2020 10 16 at 1.42.56 pm Screen shot 2020 10 16 at 1.43.03 pm Screen shot 2020 10 16 at 1.43.12 pm Screen shot 2020 10 16 at 1.43.19 pm Screen shot 2020 10 16 at 1.43.25 pm Screen shot 2020 10 16 at 1.43.32 pm Screen shot 2020 10 16 at 1.43.40 pm Screen shot 2020 10 16 at 1.43.48 pm Screen shot 2020 10 16 at 1.44.00 pm

We are currently negotiating offers on 2 Aron Court. There is an advertisement that is in process of being published for 4 Aron Court. That publication should be ready for circulation within a couple of weeks. Last week we were featured in a segment for an online series, "American Dream TV" which should air early November. There is also an e-flyer that is being prepared to be distributed to over 13,000 agents in the Bay Area. 

 

Feel free to share listing within your network for anyone who may be interested in listing in a state-of-the-art Modern home:

2 Aron Court

4 Aron Court


Screen shot 2020 10 06 at 7.40.31 pm Screen shot 2020 10 06 at 7.40.40 pm Screen shot 2020 10 06 at 7.40.59 pm Screen shot 2020 10 06 at 7.41.14 pm Screen shot 2020 10 06 at 7.41.41 pm Screen shot 2020 10 06 at 7.41.49 pm Screen shot 2020 10 06 at 7.42.00 pm Screen shot 2020 10 06 at 7.42.10 pm Screen shot 2020 10 06 at 7.42.19 pm Screen shot 2020 10 06 at 7.42.41 pm

We are pushing extremely aggressively on the marketing front in order to sell 2 Aron Court and 4 Aron Court. We secured a spot on American Dream TV, where they will be featuring the homes in their latest episode. We also reached out to Mercury News and some promising feedback regarding the ability to have the homes featured as a cover story. We have had a total of 11 showings this week. We are also redoing twilight photos in order to best capture the breathtaking views.

www.2aroncourt.com

www.4aroncourt.com


Screen shot 2020 09 27 at 8.37.50 pm Screen shot 2020 09 27 at 8.38.04 pm Screen shot 2020 09 27 at 8.38.16 pm Screen shot 2020 09 27 at 8.38.29 pm Screen shot 2020 09 27 at 8.38.56 pm Screen shot 2020 09 27 at 8.39.09 pm Screen shot 2020 09 27 at 8.39.45 pm
We just recently went live on 4 Aron Court today, and are awaiting the DOM to reset on 2 Aron Court for Monday, September 21st (target date for MLS). This upcoming week we hope to ready an E Flyer to be sent out to all agents within a 30 Mile Radius of the property. This will contain info on any specs and amenities the properties have. 
 
We should be receiving the property tour videos by tomorrow at the latest. Once edited and corrected by our team we will have them uploaded for the Live date on the 21st. 
 
Enjoy the new websites that just went live: 

Screen shot 2020 09 21 at 5.20.57 pm Screen shot 2020 09 21 at 5.21.07 pm Screen shot 2020 09 21 at 5.21.18 pm Screen shot 2020 09 21 at 5.21.32 pm Screen shot 2020 09 21 at 5.21.49 pm

On Aron Court, pictures, videos, and 3D matterport are taking place today and tomorrow for both 2 and 4 Aron Court. 4 Aron Court will be going onto the market by this Friday, and 2 Aron Court will be going to market next Tuesday the 22nd


Screen shot 2020 07 26 at 8.22.43 pm Screen shot 2020 07 26 at 8.22.54 pm Screen shot 2020 08 04 at 8.45.26 pm Screen shot 2020 08 04 at 8.46.03 pm Screen shot 2020 08 04 at 8.48.31 pm Screen shot 2020 09 07 at 4.37.21 pm Screen shot 2020 09 07 at 4.38.13 pm Screen shot 2020 09 07 at 4.39.56 pm

On Aron Court, we are bringing 4 Aron Court fresh back onto the market this week after finishing items that are completed throughout the house.  Both 2 and 4 Aron Court have been cleaned and fully staged in preparation for photos and videos, as well as open houses.  On 2 Aron Court, the final landscape work has been completed including the side yard fencing, grass, and irrigation installation as well as the exterior walkway around the left side of the house. Several finishing items are being completed in the cul de sac in order to receive final occupancy certificates, and solar panel installation across all four homes is being scheduled for completion.  The final walkthrough took place on 1 Aron Ct, and the new homeowners are moving into the home shortly.


Screen shot 2020 09 07 at 4.37.21 pm Screen shot 2020 09 07 at 4.37.33 pm Screen shot 2020 09 07 at 4.37.47 pm Screen shot 2020 09 07 at 4.38.13 pm Screen shot 2020 09 07 at 4.39.56 pm

On Aron Court, we are finalizing 4 Aron Court finishing touches in preparation for restaging of it as well as 2 Aron Court.  This staging will be highlighting the outside deck and entertainment spaces, which is one of the defining characteristics of the lifestyle 4 Aron Court provides.  On 2 Aron Court we have completed the installation of a yard fence and grass area in the large flat area to the right of the home, which is one of its most compelling selling points!  We also added a walking path connecting the front of the home around the left side of the house to the living room patio space.  This week we have interior cleaning, exterior power washing, staging, and new photos and video being taken by the sales team, led by Joe Velasco. We will be coming back to the market strong in order to properly position 2 and 4 Aron Ct. for maximum exposure.


Screen shot 2020 08 30 at 9.24.43 pm Screen shot 2020 08 30 at 9.24.53 pm Screen shot 2020 08 30 at 9.25.17 pm Screen shot 2020 08 30 at 9.25.23 pm

On Aron Court, we have partnered with one of the most prominent real estate sales teams in the mid-peninsula area to assist in getting the final two homes sold for top dollar.  We are in the final stages of solidifying listing details and timeline, and will be working on restaging the homes for updated pictures and videos. Lot 3 completion items are almost finalized and the home is almost prepared to seek it's occupancy certificate.  We will be prepping all listing materials over the next week in order to come fresh back onto the market with slightly lowered listing prices, in order to get all eyeballs on the homes!


Screen shot 2020 08 22 at 4.29.58 pm Screen shot 2020 08 22 at 4.30.09 pm Screen shot 2020 08 22 at 4.30.38 pm Screen shot 2020 08 22 at 4.30.46 pm Screen shot 2020 08 22 at 4.31.09 pm

We are working with parties who toured over the weekend and are negotiating and pushing hard to get Lot 4 sold.  We continue to finish up final remaining items on Lot 3 as we prepare to restage and relist the home.  We are discussing with an experienced agent we've worked with in the past to assist in the marketing of the final two homes in order to get them sold as soon as possible.


Screen shot 2020 08 15 at 4.44.01 pm Screen shot 2020 08 15 at 4.44.09 pm Screen shot 2020 08 15 at 4.44.42 pm

On Aron Court this week we have made substantial progress on completion items for Lot 3. All touch up painting and cleaning is scheduled to be complete early this coming week, and we are restaging in order to show off the decks, views, and most captivating parts of the house.  We should be completed and fully staged in order to come fresh onto the market by the end of this upcoming week, in time for showings next weekend.  On Lot 4, we created a new listing on MLS in order to reset days on market to zero, and have new exterior facade pictures in order to show the home off in its best light.  We are also in the process of implementing yard fencing to show off the large flat usable yard space on the side of the home. We have scheduled home tours taking place both Saturday and Sunday, and are hoping to create some competition between interested parties in order to move it into contract as soon as possible. 


Screen shot 2020 08 08 at 8.21.51 am Screen shot 2020 08 08 at 8.22.01 am Screen shot 2020 08 08 at 8.22.38 am Screen shot 2020 08 08 at 8.22.56 am

On Aron Court this past week we continued with lead follow up and several in person home tours.  We are removing Lot 3 from the market temporarily as we wrap up final finish items, complete touch up painting and a final beautification of the home.  Lot 4 has several engaged agents and buyers that we are having discussions with to work towards moving it into contract.


Screen shot 2020 08 04 at 8.45.26 pm Screen shot 2020 08 04 at 8.46.03 pm Screen shot 2020 08 04 at 8.46.46 pm Screen shot 2020 08 04 at 8.47.29 pm Screen shot 2020 08 04 at 8.47.46 pm Screen shot 2020 08 04 at 8.48.31 pm

On Aron Court, we held the homes open for private tours again this weekend, both Saturday 2-4 and today 1-3.  We had a handful of agents and buyers come through and will be following up throughout the week with disclosures and additional information as needed.  This week we also have been negotiating terms with one of the buyers we had through Lot 3 last weekend to hopefully move towards a purchase contract.  We continue to follow up with past interested parties as we work towards wrapping up all final construction items on Lot 3 and in the cul de sac.  Additionally, we have a photoshoot scheduled this evening for updated exterior shots of both 2 and 4 Aron Ct in order to capture the beautifully completed look of the homes and Aron Ct.


Screen shot 2020 07 26 at 8.21.57 pm Screen shot 2020 07 26 at 8.22.43 pm Screen shot 2020 07 26 at 8.22.54 pm Screen shot 2020 07 26 at 8.23.30 pm Screen shot 2020 07 26 at 8.24.25 pm Screen shot 2020 07 26 at 8.24.40 pm Screen shot 2020 07 26 at 8.24.58 pm
On Aron Court sales, we are following up with all interested leads and discussing specifics with several engaged parties. We are holding both 2 and 4 Aron Ct open this weekend for walk-up private home tours.  The homes will be open for viewing both Saturday from 2-4 pm and Sunday from 1-3 pm.  We already have 5-time slots reserved and are looking forward to showing off the homes to potential buyers in a safe manner.  Both property websites have been updated and can be seen here:

Screen shot 2020 07 10 at 4.20.18 pm Screen shot 2020 07 10 at 4.20.46 pm Screen shot 2020 07 10 at 4.21.15 pm Screen shot 2020 07 10 at 4.21.24 pm Screen shot 2020 07 10 at 4.21.39 pm Screen shot 2020 07 10 at 4.21.53 pm
This week at Aron Court we have been busy completing finishing items for public works in the Aron Court cul de sac as well as at 4 Aron Ct, the last home we are wrapping up final items on.  Showings have been picking up throughout the week with our continued marketing and outreach efforts.  We’ve also redesigned our property websites for the final two homes, and you can check out the site for 2 Aron Ct here: https://www.aroncourt.com/2-aroncourt-for-sale
 
As the market continues to hopefully push forward in a more positive direction, we are restarting our open houses at the final two homes 2 and 4 Aron Ct in the form of walk-up home tours this upcoming Saturday and Sunday. We look forward to inviting home buyers, agents, and interested leads to schedule a time slot to privately tour the homes in person.  Our 10k referral bonus still stands if you know of anyone who may be a suitable buyer of either of the final Aron Court homes available, so please let us know.

Ml81797199 1 1 Ml81797199 3 1 Ml81797199 9 1 Screen shot 2020 07 05 at 3.18.50 pm Screen shot 2020 07 05 at 3.19.10 pm
On Aron Court, we’re excited to announce we officially closed escrow and recorded title on the second of the Aron Court homes.  The buyers are the first to make the move into Aron Court having moved in just this weekend!
 
We have ramped up our marketing for the last two homes including rolling out a new targeted Linked in the campaign.  We also have now gone live with the new ‘day in the life’ video on 4 Aron Court, which turned out exceptionally well!  Both of the final homes were brought fresh back onto MLS with low days on market counts on both Zillow and Redfin.  As we wrap up all final items in the cul de sac as well as Lot 4 Aron Court, we continue to show both 2 and 4 Aron Court to interested parties and agents as we push hard to close the project out.

Ohj9xnkq S1gr3wbq Wew3vbua G61e5bow Ld5i3hkw

On Aron Court, we are moving to close escrow on Lot 2 early this coming week.  The buyers for Lot 4 are unable to perform on the non-contingent purchase contract we have in place, triggering liquidated damages from their deposit which was released to us, and we will be bringing the home back to the market.  Therefore, our marketing and outreach is now focused solely on Lots 3 and 4 now.  Lot 4 is fresh back on the MLS with low days on the market and is being promoted on the Zillow New Construction platform for maximum exposure.  We have temporarily removed Lot 3 from MLS in order to reset the days on market while we continue to run our targeted ad campaigns for both it as well as Lot 4.  Additionally, we shot a new high quality video on Friday showcasing Lot 3 as "A day in the life of".  We show a young couple living in and enjoying all of the incredible highlights the home has to offer including yoga on the deck, candle lit sunset dinner, and happy hour while enjoying the million dollar City and Bay views.  We'll be using the video in our targeted marketing campaigns in order to showcase the beauty and uniqueness of the Aron Court homes and the high quality lifestyle which they provide.


This past week has been a busy one at Aron Court, as we closed escrow on 1 Aron Court!  We completed our final inspections and buyer walkthroughs, in order to record the new owners and turn over the keys on Friday!  We are now shifting gears to focus on completing inspections and walkthroughs on the other two sold homes in order to receive occupancy certificates and close on them as well.  For 2 Aron Court, we had several showings with interested parties on Friday and are setting up additional tours of the homes with leads that we are bringing in from our online marketing campaigns.  It looks like San Mateo County is pushing to restart open houses sooner than later, which would be great to be able to get people through to see the home and the unbelievable views!  We also rolled out a new campaign where we are marketing a video of a candlelit dinner on the deck with amazing sunset views.  We're offering to all who are interested in the opportunity to have a delicious dinner provided to them on the deck in order to try it out! 


Screen shot 2020 05 30 at 5.36.43 pm Screen shot 2020 05 30 at 5.36.56 pm Screen shot 2020 05 30 at 5.37.12 pm Screen shot 2020 05 30 at 5.37.47 pm Screen shot 2020 05 30 at 5.38.07 pm

Last week we moved 3 Aron Court into contract and are working with the buyers to prepare for walkthroughs as we complete final inspections with the city.  We also received full sign off from the city (and occupancy certificate) for 1 Aron Court, and are signing loan and closing docs this weekend to close early next week!  On sales, we are focusing all of our efforts on getting all eyes on 2 Aron Court in order to move it into contract as soon as possible.  We’ve curated a new video of a beautiful sunset dinner taking place on the huge view deck, and are marketing the opportunity to view the home and do a test run dinner on the deck, provided by Aron Developers!  We are also using this video along with house description to implement outreach campaigns to both Facebook and Google’s internal mail communication platform, which distributes to all employees.  We continue to run high quality ads to bring in qualified leads in order to set up in person tours of the home.  Our transition to online marketing of these homes has been working well, and we’re motivated and excited to get the last of the Aron Court homes sold!


Img 4920

We’re excited to announce, on Aron Court sales this week, we moved the third of four homes (3 Aron Court) into contract on Wednesday!  After negotiations with the buyers, we executed a strong purchase contract with a significant upfront deposit released to us.  We’re now working to close escrows on all three of the homes in contract to close as soon as possible!  We have final inspections scheduled early next week for two of the three homes, after which we will move to close escrows.  We have now shifted all marketing and outreach efforts to the final home, 2 Aron Court!  We have qualified leads being generated from high quality picture and video ads indicating that this is the last chance to own at Aron Court.  We’re aggressively pushing with all leads to schedule in person showings in order to move the final home into contract as soon as possible!  


2 aron ct belmont ca 94002 usa large 005 001 04 1499x1000 72dpi 2 aron ct belmont ca 94002 usa large 006 004 05 1499x1000 72dpi 2 aron ct belmont ca 94002 usa large 007 042 06 1499x1000 72dpi 2 aron ct belmont ca 94002 usa large 019 011 18 1499x1000 72dpi

On Aron Court sales, we continue to cultivate a growing list of interested leads being brought in by our online marketing campaigns.  Activity has been up throughout the week following the updated shelter mandate which took effect on Monday, and allows for private showings and all things residential real estate transaction related to move ahead full speed.  We have had several showings of 3 Aron Court, are working with several interested parties, and are in the final stages of negotiations with one group on 3 Aron Ct.  We're hoping to solidify the terms and move 3 Aron Court into contract as soon as possible in order to shift all focus on to the fourth and final home, 2 Aron Court!


2 aron ct belmont ca 94002 usa small 005 001 04 666x445 72dpi 2 aron ct belmont ca 94002 usa small 016 014 15 666x445 72dpi

Aron Court sales are continuing to pick up momentum this week based on some key growth initiatives that we are rolling out.  This week, we went live with a direct sales outreach team which we have a dedicated team member following up by phone with every new lead that is generated.  We are now generating over 50 new leads per week, so this team is focused on connecting with them in order too set up a phone call and/or private tour of the homes with Jason, who leads our sales efforts.  This week we had 5 private home tours leading to an offer received on Wednesday.  As we negotiate contract specifics with the interested buyers, we are continuing to schedule home tours and set up calls throughout the weekend.  We also have our 2nd virtual open house scheduled this Sunday for 3 Aron Court.  Here is the link to register if you or anyone you know is interested!  As a reminder, we are offering a $10,000 referal to any investor who provides a buyer who purchases one of the remaining homes.  Additionally, we are offering free electricity for 10 years to the buyers of each of the final two homes!


2 aron ct belmont ca 94002 usa small 005 001 04 666x445 72dpi 2 aron ct belmont ca 94002 usa small 016 014 15 666x445 72dpi 2 aron ct belmont ca 94002 usa small 043 036 42 666x445 72dpi

This week on Aron Court sales, we’ve had multiple private home tours with interested buyers and agents alike through the final two available homes, 2 & 3 Aron Court.  Our strong online presence is producing a solid number of interested leads who we are actively emailing and calling to set up private showings, and we have another tour scheduled for Saturday morning at 3 Aron Court.  Additionally, he have set our second virtual home tour of 3 Aron Court for next Sunday, May 3rd at 2pm. We will be sending out the invite with webinar registration link shortly to begin growing the attendee list for the virtual tour, so please forward the invite to anyone you think may have an interest in the homes!  Both homes are being featured on the Zillow platform as promoted homes with the webinar registration link included in the listing verbiage.  We are working closely with all interested parties who have toured the home to ensure that they have all the information needed to proceed to an offer, and based on the continued activity and interest, maintain an optimistic view on moving these homes into contract over the coming weeks. In parallel, we are working with the City of Belmont to coordinate all final inspections coming out of the shelter in place (currentlyMay 3rd) to prepare for occupancy certificates and closing of escrows/close out of the project within the Month of May.


Lot 3 deck Lot 3 front Lot 3 main floor F8 3aronct 7

It's been a busy week on Aron Court sales.  From our targeted social marketing campaign, we are driving specific interest from active home buyers looking in the Peninsula area.  There are multiple interested groups for 3 Aron Court where we have been doing private home tours. Two groups are very engaged, with one of them having submitted an offer which we are actively negotiating.  As many of you may have seen, this week we scheduled a virtual open house tour for 2 Aron Court.  We have almost 20 attendees and are extremely excited to show off the beauty of the home via live webinar! Here's the link again, in case you haven't registered to attend yet. Hope to see you then, and we'll keep you updated on the progress of these final two sales and the completion of the project!


2 aron ct belmont ca 94002 usa print 006 004 05 3680x2456 300dpi 2 aron ct belmont ca 94002 usa print 012 017 11 3680x2456 300dpi 2 aron ct belmont ca 94002 usa print 025 030 24 3680x2456 300dpi 2 aron ct belmont ca 94002 usa print 034 034 33 3680x2456 300dpi

This week on Aron Court sales, we continue to innovate our online marketing presence in order to ensure we are strategically reaching active potential buyers for the homes.  On Thursday, we went live to MLS with the beautiful pictures, virtual video tour, and 3D Matterport for 2 Aron Court, the last of the four homes.  We continue our direct outreach to our list of the 300 or so most active Bay Area real estate agents, as we're seeing a majority of active home buyers working closely with an agent.  Additionally, we are leveraging several contacts in the Aron Developers network in order to broadcast information on the homes directly to internal communication threads of some of the top employers in the area, including Facebook and Google. We have also had conversations with several of the more significant online media platforms including Curbed, Forbes, Silicon Valley Business Journal, and Inman, regarding the innovative nature of the Aron Court homes. Specifically, our green approach to building ZNE (zero net energy) homes, along with the quality modern construction and breathtaking views has differentiated our homes from many in the Bay Area.  Our ramped up online presence for 3 Aron Court over the past few weeks has produced an inflow of qualified leads.  We are working closely with interested parties to get them home information virtually, and have had several in-person home tours as well.


2 aron ct belmont ca 94002 usa small 001 002 01 666x445 72dpi 2 aron ct belmont ca 94002 usa small 010 006 09 666x445 72dpi 2 aron ct belmont ca 94002 usa small 011 023 10 666x445 72dpi 2 aron ct belmont ca 94002 usa small 012 017 11 666x445 72dpi

On the Aron Court Sales front, we continue to develop new creatives for social media and online marketing campaigns with additional messaging including preferred lender interest rates in the low 2% range as well as "free electricty for 10 yrs" incentive that we are running for both of the final two homes through the month of April. We continue blasting email updates with the newly created content for Lot2 and will be completing photos and video tour and 3D matterport for Lot3 to distribute starting next week. We are working with our contact at Zillow premier to initiate a "premoted home" campaign on the platform for the two homes. It will help us more effectively promote the homes to engaged potential buyers on Zillow. We have also started a targeted outreach to talent and job recruiting individuals and companies to see how we can distribute information for 2 and 3 Aron Court to any potential Bay Area worker who are looking to relocate or purchase a new home.


F8 3aronct 4 F8 3aronct 8 F8 3aronct 13 F8 3aronct 32 F8 3aronct 34

On Aron Court sales, we recently moved 1 Aron Court into contract.  We're working closely with title and lender to ensure the transaction moves ahead smoothly to close.  4 Aron Court is ready to close upon receiving occupancy certificates at the completion of site improvements.

This week we went live with the newly produced Virtual Tour and 3D Matterport for 3 Aron Court.  In addition to targeted social media campaigns, we are directly emailing over 200 of the top producing real estate agents and teams in the Bay Area, providing newly curated content of the homes and updates through to the completion of the site.  As we finalize the finishing touches on 2 Aron Court, we will be creating similar marketing content and campaigns starting early next week.
 
We continue to engage both interested parties who attended open houses as well as leads generated via online marketing efforts, and remain optimistic in finding the right buyers for both of the homes!  As mentioned, we moved 1 Aron Court into contract just over a week ago, and while the shelter in place restrictions are creating unique challenges, we are still seeing a lot of buyers in the market that are motivated to buy and are utilizing historically low interest rates to their advantage.  We are working closely with a preferred lender who can provide interest rates as low as 2.25%.
 
We are sharpening our sales strategy for the final two homes to ensure that we are doing everything in our power to sell the homes as effectively as possible, with increased online visibility.

As for the construction items remaining, the cul-de-sac work in the public right of way remains the portion with the most number of outstanding items. We have passed inspection on the remaining concrete sidewalk and gutter sections and plan to pour those this week. Once the concrete has been poured, we will complete the asphalt in the roadway. This will make a significant improvement to the presentation of the property. Across the four homes, we are continuing to try to wrap up punch-list related items. 


F8 3aronct 4 F8 3aronct 8 F8 3aronct 17 F8 3aronct 34 Screenshot 2020 03 31 13.42.52 Screenshot 2020 03 31 13.43.39 Screenshot 2020 03 31 13.44.39 Still image

1 Aron Court is in a contract and we just got into contract on 4 Aron Court this week. 3 Aron court is currently on the market and we are in the process of re-vamping our online presence of the property. California Department of Real Estate has mandated no further open houses or broker tours for County's where shelter in place has gone into effect. As a result, virtual tours are going to be critical. We are also planning on bringing 2 Aron Court back on to the market at the very end of next week.

As for the construction, we have passed all gas inspections leading up to our gas installation date of next Monday for PG&E. Weather permitting, PG&E is scheduled to install the gas lines to all 4 houses which will complete the underground utility portion of the work for the project. We will be working to complete the remaining concrete, and then complete the final asphalt work over the next two weeks.

With the houses and the cul-de-sac nearing completion, we will also begin the process of completing final inspections. There are a number of inner-dependent inspections that all need to pass in order to receive the occupancy certificate. Once the occupancy certificate has been received, only then will we be able to close escrow on the properties in contract.


F8 3aronct 7 F8 3aronct 13 F8 3aronct 34 F8 4aronct 4 Screenshot 2020 03 14 12.50.51 Screenshot 2020 03 14 12.50.20 Screenshot 2020 02 14 15.21.39

We have been able to pre-pone our PG&E gas installation to 03/23-03/24. Once the gas line is installed, we will be backfilling the remaining trench and completing the first asphalt lift over the trench that is currently open. We will then be completing the sidewalk and gutter sections that are remaining prior to completing final coat of asphalt paving. 

 

We have had strong showing these last few weeks. Both at open houses and private showings. Due to COVID-19 concerns, we will be altering our sales strategy to showings by appointment only for the time being. Lot 4 is in contract and we are actively speaking with multiple interested parties regarding. 

 

On a daily basis, we are walking the entire property as a team to see what we can do to make the properties as attractive as possible to potential buyers and to try to incorporate any feedback we have received thus far.

 


Screenshot 2020 03 14 12.50.57 F8 1aronct 28 F8 1aronct 7 F8 1aronct 22 F8 1aronct 46 F8 3aronct 5 F8 3aronct 13 F8 4aronct 25
Lot 1-. We are working on final inspection related, landscape, and punch-list items.
 
Lot 2- The handrails on exterior decks and landscaping are yet to be complete. We are also working on painting finishing touches throughout the interior. 
 
Lot 3- Appliances, plumbing fixtures, HVAC, and electrical fixtures are nearing completion. Fire sprinkler trim will be worked on next week.
 
Lot 4- We are adding siding on the exterior to satisfy Planning final inspection correction and are wrapping up punch-list items as we wait to close on the pre-sold home.
 
Cul de Sac - We have received a preliminary gas installation date of early April. We are doing what we can right now to see if we can pre-pone this date. Once PG&E installs the gas line we will be able to complete the final paving of the cul-de-sac.

Lot 1- We are currently completing punch-list items and are scheduling final inspection related items.
 
Lot 2- Exterior handrail installation works are inspected by the vendor and it will be completed next week.  Bath hardware installation is done. We are working on the remaining punch list items, most of the items are completed and doing continuous followup with vendors to complete. 
 
Lot 3- Interior and exterior handrail installation works are inspected by the vendor and it will be completed next week. Appliances installation, Plumbing fixtures, Electrical fixture will complete till Saturday, Fire sprinkler trim, and HVAC trim works will start earlier next week. Mirror installation will be early next week.
 
Lot 4- We are currently completing punch-list items and are scheduling final inspection related items.
 
Cul de Sac - We are cleared for construction on the gas trench and are currently awaiting an installation date from PG&E.

F8 1aronct 45 F8 1aronct 46 F8 3aronct 7 F8 3aronct 34
Lot 1- Bath hardware installation works are going on and it will be completed by early next week. Punch list items are making progress.
 
Lot 2- We are working on the remaining punch list items, most of the items are completed and doing continuous followup with vendors to complete as soon as possible.
 
Lot 3- Interior wall painting works is 100% completed this week. Guest and pantry Closets installation is completed. Appliances installation, Plumbing fixtures, Electrical, Fire sprinkler trim, and HVAC trim works will start earlier next week.Door hanging completed.Mirror installation will be scheduled once plumbing fixture is done.
 
Lot 4-  Bath hardware installation works are going on and it will be completed by early next week.
 
Cul de Sac - Lot 1 final planting work will be completed after gas line trench backfilling. Lot 2 & Lot 3 planter box works are scheduled to start next week. Gas line trenching is completed and we scheduled gas line trench inspection for next weekend. Backflow water inspection is completed. Water will be connected to all lots. 

Img 4793 Img 4794 Img 4796 Img 4797 Image 1 1 Image 2 1 Image 3
Lot 1- Bath hardware installation works are going on and it will be completed by earlier next week. We are scheduling all public related works inspection early next week.
 
Lot 2- Interior handrail installation works are completed. Exterior handrail installation works are scheduled and it will be completed the next week. Siding's final painting & staining works are completed. Bath hardware installation works are going on and it will be completed by earlier next week. We are working on the remaining punching list items, most of the items are completed and doing continuous followup with vendors to complete it as soon as possible.
 
Lot 3- Interior and exterior handrail installation works will be scheduled and it will start next week. Hallway double vanity is delivered and installation is done. Siding works are completed. Wall painting works will be finished by this week. Closets installation scheduled earlier next week. The kitchen wall cabinet and kitchen island installation works are completed. Baseboard installation works are completed. Appliances installation, Plumbing fixtures, Mirror, Electrical, Fire sprinkler trim, and HVAC trim works will start earlier next week. 
 
Lot 4-  Bath hardware installation works are going on and it will be completed by earlier next week. We are scheduling all public related works inspection next week. 
 
Cul de Sac - Lot 1 & Lot 4 planter and Landscaping works are completed. Lot 2 & Lot 3 planter wall works are scheduled to start next week and drainage line, landscaping works are going on. Gasline trenching works will start early next week. Backflow water inspection scheduled this week. Water will be connected to all lots this week. All lot's walkway concrete poured this week. Interior sprinkler inspection scheduled early next week after the water connection. Occupancy certificate documentation works are going on. The street light pole's foundations are casted, pole erection works will be scheduled earlier next week. Electrical Hot Check works are going on and it will be completed by next week.

Screenshot 2020 02 14 15.16.17 Screenshot 2020 02 14 15.21.39 Screenshot 2020 02 14 15.22.04 Screenshot 2020 02 14 15.22.37 Screenshot 2020 02 14 15.23.14 Screenshot 2020 02 14 15.23.34 Screenshot 2020 02 14 15.23.58 Screenshot 2020 02 14 15.24.36 Screenshot 2020 02 14 15.25.32 Screenshot 2020 02 14 15.26.19
Lot 1-  Guest closet and Pantry shelve installation works are completed. The final painting works completed.  Except for bath hardware, we have completed all punching list works and it will be completed early next week.
 
Lot 2- Interior and exterior handrail installation works are going on and it will be completed the next week. Siding works final painting & staining works are completed. We are working on the remaining punching list items, most of the items are completed and doing continuous followup with vendors to complete it as soon as possible.
 
Lot 3- Final drywall touchup works are completed. Flooring works are completed. Interior and exterior handrail installation works will be scheduled and it will start next week. Siding works final staining & painting completed. Wall painting works are started. Closets delivered to the site, the installation will start after painting. Vanity installation completed except Hallway double vanity and it will be completed by next week. The kitchen cabinets installation works are going on and it will be completed early next week. Handrail, Plumbing fixtures, Baseboard installation scheduled early next week. Plumbing, Electrical, and HVAC trim works will start after painting. 
 
Lot 4-  Guest closet and Pantry shelve installation works are completed. The final painting works completed.  Except for bath hardware, we have completed all punching list works and it will be completed early next week.
 
Cul de Sac - Asphalt plug layer completed. Expecting water connections will be done by early next week followed by gas.

Screenshot 2020 02 07 14.47.11 Screenshot 2020 02 07 14.56.38 Screenshot 2020 02 07 14.57.41 Screenshot 2020 02 07 14.58.58 Screenshot 2020 02 07 15.00.03 Screenshot 2020 02 07 15.01.11 Screenshot 2020 02 07 15.24.41 Screenshot 2020 02 07 15.26.09 Screenshot 2020 02 07 15.27.03 Screenshot 2020 02 07 15.32.19
Lot 1-  Guest closet and Pantry shelves installation work will be starting early next week. We are working on the remaining punch list items, most of the items are completed and doing continuous followup with vendors for the remaining punch list items to complete as soon as possible. The final painting works will be completed next week.
 
Lot 2- Roof cap works are completed. Guest closet, Pantry shelves & Pony wall installation works are completed. Exterior handrail works installation scheduled early Next week and it will be completed same week. We are working on the remaining punch list items, most of the items are completed and doing continuous followup with vendors to complete it as soon as possible. Siding work final staining work are going on and it will be completed by early next week. Rain spout and gutter work completed. 
 
Lot 3- Internal drywall texturing works and external stucco works are completed. Flooring works started and it will be completed by next week. Siding works final staining will be completed by early next week. Closets delivered to the site, the installation will start after painting. The kitchen cabinets installation works are going on and it will be completed early next week. Handrail, Plumbing fixtures, Vanity installation scheduled early next week. Flooring, Electrical, and HVAC trim works will start after painting. 
 
Lot 4- Guest closet and Pantry shelve installation works will be started by early next week. We are working on the remaining punch list items, most of the items are completed and doing continuous followup with vendors for the remaining punch list items to complete as soon as possible. The final painting works will be completed next week. 
 
Cul de Sac - Electrical Hot Check works are going on and it will be completed by early next week. Wooden fence installation works are completed. Landscaping and planter box works are going on all 4 Lots. Asphalt works started and it will be completed by early next week. The street light pole erection works are scheduled and will be executed by next week. Storm line and sewer line piping works are completed. Expecting water connections will be done by next week. Pavement and Walkway concrete works will be poured by next week. Fire hydrant inspection works will be scheduled next week. Occupancy certificate documentation works are going on.

Screenshot 2020 01 31 14.40.57 Screenshot 2020 01 31 14.43.03 Screenshot 2020 01 31 14.30.17 Screenshot 2020 01 31 14.32.24 Screenshot 2020 01 31 14.32.53 Screenshot 2020 01 31 14.34.02 Screenshot 2020 01 31 14.35.19
Lot 1-  Master Closets installation completed and Guest closet installation works will be started by early next week. We are working on the remaining punching list items, most of the items are completed and doing continuous followup with vendors for the remaining punching list items to complete as soon as possible.  
 
Lot 2- Master Closets installation completed and Guest closet & Pony wall installation works will be started early next week. Exterior handrail works installation scheduled early Next week. We are working on the remaining punching list items, most of the items are completed and doing continuous followup with vendors to complete it as soon as possible. Siding works completed, the final painting will be completed by early next week. Roof cap works will be scheduled already & completed by this week. The external painting & rainspout works will be scheduled after the siding completion of works.  
 
Lot 3- Internal drywall texturing works are going on and it will be completed by next week. Stucco works are going on will be completed by early next week. Tiling works are going on and it will be completed by next week. Siding works completed, the final painting will be completed by early next week. Closets delivered to the site, the installation will start next week. Kitchen cabinets delivered today, installation works will be started early next week. Handrail, Plumbing fixtures, Vanity installation scheduled next week. Flooring, Electrical, and HVAC trim works will start after painting.  Pony wall installation works will be started by early next week.
 
Lot 4- Master Closets installation completed and Guest closet installation works will be started early next week. We are working on the remaining punching list items, most of the items are completed and doing continuous followup with vendors for the remaining punching list items to complete as soon as possible. 
 
Cul de Sac - Electricity meter installation done, All lots have electricity. Wooden fence post installation is completed, work will be completed after neighbor clearance. Landscaping and planter box works are going on all 4 Lots. Asphalt contract signed and works started. The street light foundation inspection is done, Pole erection will be completed by next week. Storm line and sewer line piping works are going on. Expecting water connections will be done by next week. Pavement and Walkway concrete works will be cast by next week. Electrical Hot Check and occupancy certificate will be obtained by next week.

60158332752  bebfc6cf 2e48 42d9 b0dd 27afdd4f958f preview 60158333753  7b2df328 c96f 4578 a46c 8ff585dc22c6 preview 2 60158335636  349b8115 9c30 4de4 a4c1 2608494dc100 preview Photo 2020 01 22 08 29 03
Lot 1-  Closets delivered and Installation works are started today, the installation will be completed early next week. We are working on the remaining punching list items, most of the items are completed and doing continuous followup with vendors for the remaining punching list items to complete as soon as possible.  
 
Lot 2- Garage door installation completed. Exterior handrail works installation scheduled early Next week. Closets delivered along with wood top and Installation works are started today, the installation will be completed early next week. We are working on the remaining punching list items, most of the items are completed and doing continuous followup with vendors to complete it as soon as possible. 75% of Siding works are finished, it will complete 100% by early next week. The final roof cap, external painting & rainspout works will be scheduled after the siding completion of works.
 
Lot 3- Garage door installation completed. Complete drywall hanging and tapping work completed. Drywall texturing will be completed by next week. We passed on external scratch coat inspection,90% of Brown coat is completed and the finish coat will be started early next week. Tiling works will be completed early next week. Siding works are completed. Closets delivered to the site, the installation will start early next week. Handrail, Plumbing fixtures, Vanity installation scheduled next week. Flooring, Electrical, and HVAC trim works will start after painting.
 
Lot 4- Closets delivered and Installation works are started today, the installation will be completed early next week. We are working on the remaining punching list items, most of the items are completed and doing continuous followup with vendors for the remaining punching list items to complete as soon as possible.
 
Cul de Sac - Wooden fence contract finalized and scheduled to start the installation works tomorrow. Landscaping and planter box works are started on all 4 Lots and drainage materials for both rainwater and planter box are delivered. Sewer line connection for all 3 lot is completed except Lot 3. Water plumbing line is completed on all 3 lots, Meter will be installed next week for water supply. Fire hydrant works are completed. Gasline piping for all 4 lot is completed. Road plate removal works are completed,  Asphalt road works will start early next week. Street light installation works scheduled next week. The remaining Walkway and Pavement block works are ongoing, and it will be completed by early next week.

60056223351  1f89479e 7094 4d9f 91ac df68357c2d0f preview 60098003041  940794bf d8fa 4311 aa9f 2cd010470a1b preview Photo 2020 01 17 07 49 10 Photo 2020 01 17 13 13 57 Photo 2020 01 17 13 17 56 Photo 2020 01 17 13 31 07 Photo 2020 01 17 13 31 30
Lot 1-  We scheduled closet installation on 16th January. We are working on the remaining punching list items, most of the items are completed and doing continuous followup with vendors for the remaining punching list items to complete as soon as possible.
 
Lot 2- Siding works started will be completed by next week. Both Lower and Upper deck tiling is completed, Exterior handrail works installation scheduled Next week. Penny wall wood top, Garage door installation, and Closets installation scheduled on January 16th. We are working on the remaining punching list items, most of the items are completed and doing continuous followup with vendors to complete it as soon as possible. The final roof cap, external painting & rainspout works will be scheduled after the siding completion of works.
 
Lot 3- Drywall taping is going on and whole drywall works will be completed by next week. The external scratch coat is completed and scheduled for the inspection today. Brown coat will be started right after an inspection. Waterproofing inspection completed and tiling works are going on. Siding works started will be completed by next week. Closets installation scheduled on January 16th. External stucco works will be scheduled to complete by January 23rd. Handrail, Plumbing fixtures installation scheduled next week.
 
Lot 4- We scheduled closet installation on 16th January. We are working on the remaining punching list items, most of the items are completed and doing continuous followup with vendors for the remaining punching list items to complete as soon as possible. 
 
Cul de Sac - Chain link fencing is completed. Wooden fence contract finalized, work will start early next week. Landscaping and planter bed work started for both Lot 1 & Lot 4 and drainage pipes for the same also ordered.  Backwater flow inspection is completed, working on it connect the main line. Gasline piping for all 3 lot is completed except lot 3 and it will be completed by today. Road plate removal works are started, Asphalt road works will start early next week. Street light foundation inspection completed. The remaining Walkway and Pavement block works will be started immediately after utility connection to the house. sewer and storm line connection works are ongoing.

Img 8141 Img 8142 Img 8143 Img 8144 Img 8145
Lot 1-  We are working on the punch list items, most of the items are completed and doing continuous followup with vendors for the remaining punch list items to complete as soon as possible.
 
Lot 2- Siding installation will start early next week. Exterior handrail works installation scheduled next week after the lower deck floor tiling. pony wall wood top, garage door installation, and closets installation scheduled on January 16th. The final external painting will be started after siding works.
 
Lot 3- Both wall and ceiling drywall hanging are completed. Roofing works completed. External lath papering works completed. Drywall tapping, waterproofing inspection, lath inspection, external scratch coat and tiling work planned early next week. Siding quote approved and installation will start early next week. Closets installation scheduled on January 16th. External stucco works will be scheduled to complete by January 23rd.
 
Lot 4- We are working on the punch list items, most of the items are completed and doing continuous followup with vendors for the remaining punching list items to complete as soon as possible. 
 
Cul de Sac - Both wooden & chainlink fence contract finalized, work will start early next week. Landscaping and planter bed work started for both Lot 1 & Lot 4 and working on it to complete ASAP. Backwater flow installation completed all 4 lots, scheduled for inspection on early next week. Gasline piping will be connected to the house by earlier next week.  Asphalt road works will start early next week. Street light foundation inspection planned early next week. The remaining Walkway and Pavement block works will be started immediately after utility connection to the house. 

Img 4258 2 Img 4259 Img 4260 Img 4261 Img 4262 Img 3951 Img 3954 Img 3952 Img 3953
Lot 1-  We are working on the punching list items, most of the items are completed and doing continuous followup with vendors for the remaining punching list items to complete as soon as possible.
 
Lot 2- Exterior handrail works installation scheduled Next week. We are working on siding quotes, expecting will be finalized earlier next week. Mirror installation completed. Penny wall, Wood top, and Closet work scheduled for next week. The baseboard painting is completed. We are working on the punching list items, most of the items are completed and doing continuous followup with vendors for the remaining punching list items to complete as soon as possible. Final external painting scheduled next week.
 
Lot 3- Door painting is completed. Drywall hanging works are ongoing. Waterproofing inspection, Lath Inspection, External scratch coat and Tiling work planned early next week.  We are working on siding quotes, expecting will be finalized earlier next week. Closet installation works planned early next week. External stucco will be completed by January 23rd.
 
Lot 4- We are working on the punching list items, most of the items are completed and doing continuous followup with vendors for the remaining punching list items to complete as soon as possible. 
 
Cul de Sac - Electrical inspection completed. Landscaping and planter bed work started and working on it to complete ASAP. Waterline, Gasline piping will be connected to the house by earlier next week.  Asphalt road works will start after the Christmas holidays. Street light foundation inspection planned early next week. The remaining Walkway and Pavement block works will be started immediately after utility connection to the house.

Screen shot 2019 12 27 at 5.17.35 pm Screen shot 2019 12 27 at 5.17.18 pm Screen shot 2019 12 27 at 5.17.04 pm Screen shot 2019 12 27 at 5.16.56 pm Screen shot 2019 12 27 at 5.16.47 pm Screen shot 2019 12 27 at 5.16.41 pm
Lot 1-  We are working on the punching list items, most of the items are completed and working for the remaining punching list items to complete as soon as possible.
 
Lot 2- Inside handrail works are done. Exterior handrail works installation scheduled Next week. We are working on siding quotes, expecting will be finalized earlier next week. Installation of Mirror, penny wall wood top works scheduled for next week. We have started to door hardware installation and working on snag lists. Final painting scheduled next week.
 
Lot 3- Painting is ongoing for Fabricated doors. Wall frame Insulation work is completed and passed on the inspection. We scheduled drywall hanging and Waterproofing inspection early next week. Tiling works will start immediately after obtaining the approval on waterproof inspection. The external scratch coat is ongoing. We are working on siding quotes, expecting will be finalized earlier next week.
 
Lot 4- We are working on the punching list items, most of the items are completed and working for the remaining punching list items to complete as soon as possible. .
 
Cul de Sac - Landscaping and planter bed contract finalized, work will start early next week. All works finalized and assigned vendors for each of them. Road mud cleared this week. Asphalt road works will start after the Christmas holidays. Waterline, Gasline piping done up to the property is done. Sewer piping is done for lots 1 & 2. scheduled street light & Electrical inspection on next week.

59855618394  e657f3fa a679 4dee 8e30 2ee935fce774 preview 59855631503  3e324377 94bd 4ac1 9cca b20ccd6091a2 preview 59855642007  ed489292 5bdf 48ce b5c0 58705cf5a3f9 preview 59855645825  ee141c85 6b55 46da bcab b2491deb7e41 preview 59855662773  cd546fc7 68d5 497c a254 e76cd19bb140 preview 59855680787  10e62bb5 dbb1 478c 9f2c 6815cb1c9cc0 preview Screenshot 2019 12 20 12.15.10
Lot 1-  We are working on the Punching list items and doing continuous follow up with vendors to complete it as soon as possible.
 
Lot 2- Application installation completed. We are working on siding quotes, expecting will be finalized earlier next week. Mirror, Handrail, wood top installation will do next week. We have started to finish carpentry door hardware items and working on snag lists.
 
Lot 3- Installation of exterior doors are completed and interior door installation is ongoing. Insulation work is completed expecting inspection early next week. We are going to start Drywall works, Waterproofing and Tiling by next week. Exterior stucco works are ongoing.  We are working on siding quotes, expecting will be finalized earlier next week.
 
Lot 4- We are working on the Punching list items and doing continuous follow up with vendors to complete it as soon as possible.
 
Cul de Sac - Paver works are ongoing. we formed and poured the curb wall this week. And also, we are working on Drainage, Sewer connection, landscape, fencing, Storm and asphalt contracts. Hopefully, we finalize pending contracts early next week

Fe5a4c6f ee57 4261 8e82 428a3df06a55 A8225fd4 d6f5 4133 84b9 11bf226a248a F80a219c 7f7c 4ab4 814d 75d00a213906 Cf8ab261 72d1 49d4 8224 c9f3302f32da 143a0b96 30f1 4a3e 8e09 1e3ef94b632c 2c6a17d4 9592 4115 b519 12aaf755a7ca 61c3893d 96a6 4112 b4b7 aa2cc674b003 C5b84197 1ebd 45fa a9ab 792daf182526 59760684110  f4c0f15c 86f9 4727 a268 a3902f13a145 3ce2360a bd7a 49e7 8f5d 296169bc93f7
Cul de Sac - Paver works are ongoing. we poured retaining concrete wall this week. we passed formwork inspection this week for the curb. and also we finalized landscape, fencing, and asphalt contracts. We planned to pour curb in the upcoming week.
 
Lot 1-  We are working on the  punchlist items and doing follow up with vendors to complete it as soon as possible.
 
Lot 2- Completed installation of light fixtures. We have started to finish carpentry works like doors & its hardware items. Appliances have been ordered, will do installation next week. Mirror, closet, wood top quote approved and production started.
 
Lot 3- Installation of interior and exterior doors. we passed rough Electrical, Plumbing and frame this week. we are working on the siding quotes for the exterior. we working on frame-filling works as well expecting to finish it next week. we will start interior paneling works by next week.
 
Lot 4- We are working on the punchlist items and trying to complete it asap
 
 

0e8c7edd 3ba1 4093 bb98 f898c48f2845 9835c6f5 8cf7 455a 96fe 15f02de9b174 545275b4 1167 4d4b 9e66 04dbe5847f1e 0787858b e5c4 4f72 b404 c0bf51321204 Be2d4dfb 3599 4fb0 b52e 904d23eb1578 C77999eb bf0a 40ca 969e 042862deab9a Dfc8307c b7b4 4590 9ea9 7cf0ed0bf69e E216edea cfe2 4537 87d3 5fcb71ac7b92

On the cul-de-sac, the last remaining section of retaining wall has been poured. The curb, gutter, and sidewalk, is approximately half complete. We are cleared for construction on the electrical install for PG&E and are just now awaiting the gas engineering from them and also to begin the storm drain. 

Lot 1 we are working on the punch-list items and the site work.

Lot 2, we are working on the finish carpentry and prepping for the appliances install and the handrails.

Lot 3, we are awaiting all trades rough inspection to enable us to be able to insulate and drywall.

Lot 4, punch-list items are making progress and we are working on site work.

 

 


Whatsapp image 2019 11 29 at 9.16.42 am Whatsapp image 2019 11 29 at 9.26.41 am Whatsapp image 2019 11 29 at 9.22.19 am Whatsapp image 2019 11 29 at 9.22.13 am Whatsapp image 2019 11 29 at 9.21.58 am Whatsapp image 2019 11 29 at 9.20.06 am Whatsapp image 2019 11 29 at 9.18.01 am Whatsapp image 2019 11 29 at 9.16.34 am 3d627a44 6901 494a 8d27 6e25a1c2cfe8 54ddd936 3ec5 454e a132 30599a49c896
Aron Court Lot 1: We are actively negotiating with parties and completing remaining punch list items.
 
Aron Court Lot 2: Cabinets, exterior tile, and finish fixtures have been installed on the interior. We will be completing finish paint on the interior and installing handrail in the coming weeks. We will also be installing appliances.
 
Aron Court Lot 3: Mechanical and plumbing has signed off for rough inspection. We are having framing and electrical rough inspection on Monday of next week prior to insulation and drywall.
 
Aron Court Lot 4: Interior work, with the exception of punch list items, is complete. We are working on connecting the sewer and water on the site. 
 

Screen shot 2019 11 22 at 2.18.03 pm Screen shot 2019 11 22 at 2.18.13 pm Screen shot 2019 11 22 at 2.18.25 pm Screen shot 2019 11 22 at 2.18.38 pm Screen shot 2019 11 22 at 2.18.49 pm Screen shot 2019 11 22 at 2.19.07 pm Screen shot 2019 11 22 at 2.20.19 pm Screen shot 2019 11 22 at 2.20.28 pm Screen shot 2019 11 22 at 2.20.40 pm

Cul-de-sac: We are currently working to form the sidewalk and the gutter along the cul-de-sac. We have completed the water main and currently working to extend the laterals to the individual properties. The gas and electric trench remain open as we wait for PG&E to install services.

Lot 1: We are actively negotiating offers and are working to complete the site work. 

Lot 2: Cabinets, stucco, flooring, and trim have been completed and we are working on the exterior stone and siding. Interior tile work has been completed and is now moving on to exterior decks. 

Lot 3: Rough work is nearing completion. We have passed the first of the inspections and anticipate to receive other sign-offs next week. The next step will be to insulate and hang drywall on the interior. On the exterior, roofing is underway and expansive waterproofing on the decks. Scaffolding has been erected around the perimeter and building paper will start to wrap the house next week.

Lot 4: Construction is complete with the exception of the punch-list items on the interior.


Img 0956 Img 4543 Img 4604 Img 6177 Img 6870 Img 7240
Cul-de-Sac: PG&E completed the Gas cut off for the old gas line on the property. Water line is being installed and is 50% complete and we expect it to complete by next week. 
 
Lot 1- Currently we are working on the punch list items on Lot 1. With power and gas on the longer pole we have set up temporary power to energize Lot 1 while we are waiting on power from PG&E. We are still working to get final inspection of the building on track and preparing the marketing material to go live on MLS.
 
Lot 2- Complete installation of vanities and cabinets is expected to complete by end of this next week including countertop and back splash. With Hardwood flooring completing this week we are all set for the pre site appliances  Inspection next week. With final coat of stucco completing this week we are all set to start exterior tiles and stones by early next week. 
 
Lot 3-The rough trades are in full swing inside the house. We passed rough mechanical this week and expecting to pass electrical, framing and plumbing inspection by end of next week. On the exterior all of next week is planned for waterproofing the decks, start roofing, Paper & Lath.  
 
Lot 4- We completed the tiles and railings including the exterior patio. We installed the hoods on the interior. We are also pushing to complete punch list items and preparing for a plan to bring the property to market. 

Img 4914 Img 4915 Img 4916 Img 4918 Img 4921 Img 4923 Img 4924 Img 4926
Utilities, cul-de-sac retaining walls, and sidewalk work is coming along. We are working to try to complete the invasive underground aspects of the project prior to the rain. PG&E continues to be the long pole on the project and we are working with all agencies and contacts in order to try to expedite. 
 
Lot 1- Staging has been completed and rough cleaning on the interior has been completed. Temporary power has been set up to energize Lot 1 while we are waiting on power from PG&E. Over the next couple weeks, we will be working to get final inspection of the building and preparing the marketing material to go live on MLS.
 
Lot 2- First round of painting inside the house has been completed and we are looking to complete installation of vanities and cabinets by end of next week. Hardwood flooring is on track as well and scheduled to complete by the end of next week. On the exterior we are completing final coat of stucco by next week. 
 
Lot 3-The rough plumbing, mechanical, and electrical is scheduled to be completed by next week and once we pass the fire drill inspection the following week we start with insulation inside the house. Scheduled to start stocking the drywalls in the same week and start hanging drywalls the following week. 
 
Lot 4- Railing is making good progress only remaining portion is the patio which is scheduled to be completed by next week. We are pushing to complete punch list items and preparing a plan to bring the property to market. 

Img 4699 Img 4696 Img 4694 Img 4693 Img 4692 Img 4691 Img 4690

Cul-de-sac: Lower driveway retaining wall was completed. Dirt off haul and compaction of dirt behind behind Lot 1 wall is 50% complete. Gas disconnect inspection was passed.

 

Lot 1 - We had about 200 parties attend the open house last weekend. There is another open house this weekend. Please feel free to drop by: Sat - Sun: 1pm - 4pm

Lot 2 - Painting is underwayand is expected to complete mid next week when we start installing Cabinets and Vanities. Scratch was completed on the exterior and passed inspection.

Lot 3 - We passed sheer inspection earlier this week. Rough HVAC is 75% complete. Framer is working on stairs, windows, exteror doors and pick up.

Lot 4 - Railing is being installed, gutters were installed. House is coming to completion soon.


Img 4249 Img 4250 Img 4251 Img 4252 Img 4253 Img 4254 Img 4255 Img 4256 Img 4257 Img 4258 84 f8207302402356  mls 14 f8207302402515  mls 10 f8207302402511  mls 27 f8207302402528 mls 22 f8207302402523  mls

Cul-de-sac: Driveway retaining wall footing was poured today. we are expecting to complete the retaing wall early next week

Lot 1: Lot 1 is 100% complete and house is fully staged for the Open House this weeken. Note that even after we go in a contract we will have to wait on closing escrow till all the cul-de-sac work finishes.

 

Lot 2: Dry wall 100% completed. Painting starts Monday. On the exterior we are starting scratch coat next week and hopefully will pass inspection by the end of next week. 

 

Lot 3: Sheer inspection passed today. Rough plumbing and rough HVAC will start on Monday. Windows, doors, soffits to start installation next week. 

 

Lot 4: House is 95% complete. Painting touch ups completed. Final electrical, plumbing and HVAC units installed. Railing will be completing towards the end of the week. We are pushing to complete punch list items and preparing a plan to bring the property to market. 


02 f8207302402502  mls 21 f8207302402522  mls 10 f8207302402511  mls 35 f8207302402307 mls 65 f8207302402336 mls 57 f8207302402329 mls 50 f8207302402322 mls 05 f8207302402505  mls Img 3873 Img 3877 Img 3879
Utilities, cul-de-sac retaining walls, and sidewalk work is coming along. We are working to try to complete the invasive underground aspects of the project prior to the rain. PG&E continues to be the long pole on the project and we are working with all agencies and contacts in order to try to expedite. 
 
Lot 1- Staging has been completed and rough cleaning on the interior has been completed. Over the next couple weeks, we will be working to get final inspection of the building, energizing the house with temporary power while waiting for power from PG&E and preparing the marketing material to go live on MLS. We will be taking professional pics next week.
 
Lot 2- Drywall work is 50% and paper and path on the exterior is complete. Tile work is making progress and the rest of the interior work will be making strides once finishing of drywall is complete.
 
Lot 3- Roof framing is complete and the sheathing on the exterior is making progress. We are aiming to complete sheathing end of next week. Once sheathed the rough plumbing, mechanical, and electrical will begin.
 
Lot 4- Railing and painting is making progress. We are pushing to complete punch list items and preparing a plan to bring the property to market. 
 

Img 3193 Img 3194 Photo 2019 10 11 07 48 09 Photo 2019 10 11 07 48 16 Photo 2019 10 11 07 48 27 Photo 2019 10 11 07 48 48 Img 4457 Img 4458 Img 4460 Img 4459
Lot 1: Appliances are installed. Final coat of painting and touch ups is getting completed Monday morning next week. The house all ready to be staged by early next week. 
 
Lot 2 : We passed Drywall Screw Inspection as well as Lath Inspection. We expect to complete And start painting by end of next week. Outside the house, we are ready to start scratch coat by early next week. 
 
Lot 3: Framing of lower level is complete and we are all set to pass sheer Inspection by end of the following week. Outside the house we are all set to backfill the retaining walls.
 
Lot 4: Railings on the interior and exterior is expected to complete by this week. Cabinets and counter tops are installed. The final coat of painting is scheduled to complete by end of next week. 
 
Cul De Sac- Utiltiies work is in full swing with entire site having open trenches for PGE Gas, ELectricity. Site access and parking are limited. The team is working as aggressively as possible to get through this portion of the project . We still need to put in the sewer, storm and water lines which the team will work over the next couple of weeks

 


Img 3289 Img 3290 Img 3291 Img 3292 Img 3293 Img 3294 Deb9a1c6 a50f 4d4d 8944 f393b23ab101 Img 3243

Lot 1: Appliances delivery on Lot 1 is scheduled for early next week. We have completed all hand railings on the interior and exterior of the house. We are getting ready to stage the home.

Lot 2: We passed insulation inspection this week and shower pan inspection this week. Drywall hanging is going on and we have scheduled the screw inspection for next Tuesday. Next week we are planning to complete drywall hanging, mudding and taping and the following week the painter can start. Outside the house, all retaining walls are completed. Scaffolding is completed. Lath in progress.

Lot 3: The truss calculation has been passed by the city and the trusses are getting delivered by end of next week. Two floors are framed and framing for 3rd (top) floor underway. We are looking forward to pass the Sheer Inspection by mid October. 

Lot 4: We are expecting the hand railing to be completed by this week. All the electrical trims on Lot 4 is also expected to be completed by this week. The painter is scheduled to start with the final coat starting next week. Appliances are expected to get delivered at site by today.  

Cul De Sac- Utiltiies work is in full swing with entire site having open trenches for PGE Gas, Electricity. Site access and parking are limited. The team is working as aggressively as possible to get through this portion of the project. The water connection on street was completed this week.  We still need to put in the sewer and storm lines which the team will work over the next couple of weeks. 


Img 3066 Img 3067 Img 3068 Img 3069 Img 3070 Img 3071 Img 3072 Img 3073 Img 3074 Img 3075 Img 3076
Lot 1: Final drywall touch ups and second coat of painting on the interior has completed. Railing installation on stairs is expected to complete early next week. Light fixtures installation on the interior is expected to complete by end of next week. 
 
Lot 2:  We passed all the rough trades Inspection this week and insulation has started on the interior. Hoping to pass insulation Inspection by Tuesday of next week post which we can start hanging sheet rocks. We passed the final inspection on block walls on the exterior today. 
 
Lot 3: Framing of the house is in full pace and we are expecting to pass sheer Inspection in a week or two. Outside the house, all the retaining walls on the home are expected to be done soon. 
 
Lot 4: All flooring including stairs is scheduled to be completed by end of this week. Railings installation will start on the interior start next week and we are hoping to finish by end of the week. 
All interior final light fixtures have been installed. 
 
Cul De Sac- Utiltiies work is in full swing with entire site having open trenches for PGE Gas, ELectricity. Water connection is scheduled for next week. Site access and parking are limited. The team is working as aggressively as possible to get through this portion of the project . We still need to put in the sewer, storm and water lines which the team will work over the next couple of weeks. 

Img 2800 Img 2810 Img 2811 Img 2885 Img 2886 Img 2887 Img 2888 Img 2889

Lot 1: Final touch ups of drywall is completing this week and we will complete the final coat of painting next week. Final plumbing finishes and final light fixtures are also schedule to complete by end of next week. 

Lot 2: Fire sprinkler set up is being done and we have the inspection scheduled for next Tuesday. We have all rough trades inspection schedule for next week and once we pass we plan on starting with insulation on the interior. We have scheduled the Drywall materials to be stocked on site by next week. Outside the house, retaining walls for the driveway are formed and we are hoping to pass the retaining walls inspection scheduled for next week. 

Lot 3: Framing of the house is in full pace and looking at how things are shaping we are hoping to get the sheer inspection done in two weeks to come. Outside the house, all the retaining walls are formed and we are hoping to start back filling later next week. 

Lot 4: Flooring is all set to complete by end of this week. Following next week we have scheduled installation of railing on the stairs on both interior and exterior of the house. 

Cul De Sac- Utiltiies work is in full swing with entire site having open trenches for PGE Gas, ELectricity. Site access and parking are limited. We are trying to the get the water connection done on street early next week. The team is working as aggressively as possible to get through this portion of the project .


Img 1837 Img 2589 Img 2590 Img 2592 Img 2593 2 Img 2594 Img 2603 Img 2604 Img 2605 Img 2608 Img 2609 Img 5209 Img 8146 Img 8631

Lot 1: Flooring installation is complete on Lot 1 and we've scheduled interior railings to be installed starting next week. All set to pass pre-site appliances inspection this week and arrange for delivery of appliances in weeks to follow. 

Lot 2: Rough plumbing, Rough mechanical, Rough electrical and Fire Sprinklers are being worked on. Planning to have all rough trades like rough plumbing, Rough electrical, HVAC and fire sprinklers set up done and pass rough trades inspection next week.  Outside the house, all retaining walls are expected to be completed soon and we're getting waterproofing done by end of next week. 

Lot 3: Framing of lower level is complete and the team is working on framing the middle floor of the house. Outside the house, all the retaining walls on the home are expected to be done ready for waterproofing by end of the week. 

Lot 4: Cabinets and counter tops are installed. All flooring is scheduled to be completed by end of next week. Following week we are planning to get the final coat of painting done on the interior. 

Cul De Sac- Utiltiies work is in full swing with entire site having open trenches for PGE Gas, ELectricity. Site access and parking are limited. The team is working as aggressively as possible to get through this portion of the project . We still need to put in the sewer, storm and water lines which the team will work over the next couple of weeks


58948684992  ad538894 505a 4301 a16f 6c7a9bbf853c 58948685925  1cd7c1e7 72ba 41a6 bb48 7c0c205cf6cd 58948689766  85705834 b7ce 4b81 9b51 63be8830b7a1 58948703277  d3edcc82 af89 4620 ad11 08679babea3a 58948736714  bf957290 5a3a 4d55 a0fe f8a394a77286 58948740959  f422936b ef2a 4bb8 8d7e 118b64958c95 58948743433  55b761fd 0104 4c24 9f3c f86a988b2397 58948754887  87f6655c 2f60 4ab0 a005 768fd1146031 58948756397  ea0f7dba cf5b 4e40 9779 cdb2b273f604 58948757413  9efcdf8a fbce 4497 965e fa7cfff32921

Lot 1: Flooring installation on 2nd floor is complete and 1st floor flooring is being worked on. Cabinets and counter-tops are also being installed.

Lot 2: We passed Sheer inspection this week. Rough plumbing and Rough HVAC is being worked on. Next week, we plan to being Rough electrical as well as fire sprinklers. Outside the house, retaining walls for the driveway are formed and the concrete will be poured next week.

Lot 3: Framing of lower level is complete and the team is working on framing the middle floor of the house. Outside the house, 50% of the retaining walls on the home were poured this week. The remaining are being formed next week.

Lot 4: Cabinets and counter tops are installed. Flooring material is delivered. Flooring will begin early next week.

Cul De Sac- Utiltiies work is in full swing with entire site having open trenches for PGE Gas, ELectricity. Site access and parking are limited. The team is working as aggressively as possible to get through this portion of the project . We still need to put in the sewer, storm and water lines which the team will work over the next couple of weeks

 


Img 1992 Img 1993 Img 1994 Img 1995 Img 1996 Img 1997 Img 1998 Img 1999 Img 2001 Img 2002 Img 2003

Lot 1:

On the exterior, we have completed final coat of Stucco this week. Will start hardwood flooring installation going tomorrow onward.. On the inside, the finish coat of painting is expected to get completed by early next week. Garage doors are installed and exterior hand rails installation is scheduled to start next week . 

 

Lot 2:

Framing is almost complete and we are scheduled for Shear Inspection early next week. All the interior doors are schedules to arrive next week. All the rough trades are expected to start working inside the house starting early next week or two. The retaining wall footings were inspected and passed this next week. We are preparing to pour concrete on the footings next week. 

 

Lot 3:

Framing of the house if in full progress and all walls are standing. We will be getting the truss calculations next week, post which we can get the truss delivered. Also the retaining walls outside the perimeter are being constructed and we have passed retaining walls inspections this week.

 

Lot 4: 

On the interior, finish coat of painting is completing next week. All the cabinets and vanities were installed this week next week and bathroom vanities are expected to be installed by this weekend. All front doors have been installed and exterior tiles installation completed.  Final plumbing and light fixtures are ready to be installed from next week.  


Img 4043 Img 4633 Img 6486 Img 6603 Img 7772 Img 7953 Img 8522 Img 8848 Img 1496

Lot 1:

On the exterior, we will complete final coat of Stucco early next week. Will start stocking hardwood flooring material next week. On the inside, painting is expected to get completed by this weekend. Vanities are expected to finish installation by this weekend and garage doors to be installed next week. 

 

Lot 2:

Framing of both floors is almost complete and we are gearing up for the Shear Inspection by next week. Measurement of all opening have been taken for the windows installations, windows are expected to arrive in a couple of weeks. All the rough trades are expected to start working inside the house within a week or two. The retaining wall construction outside the perimeter of the building is in full swing and we are all set to drop cages and get them inspected early next week. 

 

Lot 3:

Framing of the house if in full progress and all walls are standing. Also the retaining walls outside the perimeter are being constructed and we have inspections for the retaining walls next Tuesday. 

 

Lot 4: 

On the interior, painting is completing this week. We are getting ready to install cabinets early next week and bathroom vanities are expected to be installed by this weekend. All front doors are scheduled for delivery and installation early next week. We are stocking hardwood flooring material and start installation in couple of weeks. On the outside, the final stucco coat has completed. 


Img 1535 Img 1533 Img 1532 Img 1531 Img 1530 Img 1529 Img 1528 Img 1527 Img 1526 Img 1524 Img 1523

Lot 1:

On the exterior, we completed brown coat of Stucco and the color mixes for the final coat is finalized.  On the inside, painting of doors is complete and first coat of painting is underway.

 

Lot 2:

Framing of both floors is complete and we are waiting for Roof Trusses to be delivered which were approved this week. Also the layout of the mechanical room, duct work, soffits has been finalized. The architect has completed making the plans modifications to be submitted to the city for the roof lowering changes as well as the addition of windows to the living room. We expect roof trusses to be on site early next week and be able to have sheer inspection in 2 weeks, ready for all rough trades to work in the house. The retaining wall construction has also started outside the perimeter of the building.

 

Lot 3:

Framing of the lower floor is underway and all walls are standing. Also the retaining walls outside the perimter are being constructed and lowest walls passed inspection earlier today.

 

Lot 4: 

On the interior, painting is in full swing and we are getting ready to install cabinets, bathroom vanities, hardwood flooring over the next couple weeks.  We also expect to do the finish coat of stucco with approved color mix next week.


Img 1275 Img 1276 Img 1277 Img 1278 Img 1279 Img 1280 Img 1281 Img 1282 Img 1283 Img 1284 Img 1285 Img 1286 Img 1288 Img 1289

Lot 1: Drywall is 100% completed. Interior Tiling is 75% completed. Scratch Coat of Stucco Completed and Passed Inspection. Painting will be Starting on 8/5.

Lot 2: Both Floors have been framed and sheered(plywood complete). We have modified the floor plans, added windows  to expand the gorgeous views and dropped roof height from 14' to 10' to in a section of house to open up the views for Lot 1 home. Plumbing, HVAC, Electrical subcontractors have walked the job and ready to start immediately upon passing of Sheer inspection. We are awaiting Roof Truss delivery and installation upon which we can call for Sheer Inspection.

 

Lot 3: Framing has started. There are 6 retaining walls that need to be built outside the house and construction of retaining walls has started. Today 2 of them passed rebar inspection and concrete will be poured this weekend.

 

Lot 4: Drywall is 100% complete. Painting underway. Tile installation on the interior of the home is 100% complete. On the exterior, Siding installation is 100% complete. For Stucco, Brown Coat is 100% completed. We are waiting on final color mix and as soon as that's finalized, final coat of Stucco will be completed.


1eae11ef 90d9 4318 9e3e de83ad9479c1 9b256d7c ad35 4720 86a2 879d6094af82 9887f8ca 8e49 4ed9 b946 5c6c4c4d3e00 A73aee80 659a 485a be42 79e9036fe569 B7bab08f 21e9 486b 8402 30f93be2596a F66891ea 6550 4b62 821b a2e90c426c8b 287fa4ad 0e10 4457 91b0 38434281cf4d A32e58dd c6a4 451e 8e9e 811f82554e86 Ca773dcf 3799 422d 9ff5 aebbe1056ae9 0002df69 3c99 4036 b6f9 2d547ad06e6b 89db2c67 e423 4b09 bfa4 289bd8038450 51ae24ac 73d6 49a6 97bf 1a1f0a6c8f64 Ebc20da2 fc9f 4b8e 9976 30ead3d310c9

LOT 1:

Retaining Walls on Lot 1 has been poured. Lath 100% completed including corners and expansion joint, all set to start scratch coat next week and scratch coat inspection is scheduled for Friday (8/2) . Drywall to be 100% completed including prep and sand by next Friday (8/2). Painting contract has been finalized. 

 

LOT 2:

Framing in progress looking forward to schedule sheer inspection.All windows have been delivered. 

 

LOT 3:

Waterproofing and backfilling tier 2 and 3 is 100% completed. Rebar footing inspection scheduled on 7/30 and looking forward to pour on 7/31. Lumber is delivered on site for framing to start. 

 

LOT 4:

Stucco Brown coat is completed on the outside. Drywall to be 100% completed including prep and sand by next Tuesday (7/30) . Painting to start by next week. Tiles installation inside the house to be completed by 7/27. 

 

Cul De Sac:

Site Utilities engineering design for PG&E, Water, Storm, Sewer is being finalized and contracts negotiated with general engineering subcontractors. Work is expected to begin within next 2 weeks.


Img 2310 Img 2308 Img 2307 Img 2306 Img 2304 Img 2303 Img 2302 Img 2254 Img 2253

LOT 1:

Lath completed and Lath inspection passed. Drywall hanging and taping is completed. Shower pan waterproofing complete and inspections passed. Topping and skimming will be worked on next week. 

LOT 2:

Framing of 2nd floor walls in progress.

LOT 3:

Waterproofing behind retaining walls and backfilling  to start framing is completed. Looking forward to gettting framing started ASAP.

LOT 4:

Stucco Scratch coat is completed on the outside. Drywall Topping is completed on the inside. Drywall skimming in underway and will continue next week. Also Outside retaining walls are being formed and concrete will be poured on 7/23.

 

Cul De Sac:

Site Utilities engineering design for PG&E, Water, Storm, Sewer is being finalized and contracts negotiated with general engineering subcontractors. Work is expected to begin within next 2 weeks.


Img 2142 Img 2136 Img 2135 Img 2134 Img 2133 Img 2131 Img 2130 Img 2129 Img 2125 Img 2119

LOT 1:

Paper complete and Lath are in progress on the outside.

Drywall hanging is complete on the inside and Drywall inspection is scheduled for Monday 7/15.

 

LOT 2:

Framing of lower floor complete, subfloor for main floor complete. Next weeks, walls will stand for the main level.

 

LOT 3:

Foundation is complete for the home. 

Waterproofing and backfilling behind the retaining wall is in progress. 

Shortly thereafter framing will commence.

 

LOT 4:

Outside Lath competed and passed inspection. 

Sratch coat of stucco is in progress.

Siding installation is in progress

On the inside, Drywall Hanging is complete and passed Screw inspection.

Next week the Drywall taping and bathroom waterproofing will be completed.


Img 2690 Img 0481 Img 2030 Img 6890 Img 2701 Img 5284 Img 8670 Img 9824 Img 8008 2

LOT 1:

  • All trades inspection passed.
  • Insulation has started.
  • Dry wall material is stocked and will begin installation on Monday after we pass insulation inspection on Monday.
  • Installation of all doors  is complete.

 

LOT 2:

  • Framing is underway at the lower level.
  • In 2 weeks we are planning to call for sheer inspection.

 

LOT 3:

  • Pre pour inspection for the last wall passed on Wednesday.
  • Waterproofer completed surestop today.
  • Foundation sub is working towards closing the forms by forms by tomorrow and concrete is planned to be poured on Monday. This is the last piece of concrete on the last of the four homes on this project. We are excited about this milestone as the framing will start soon after that.

 

LOT 4:

  • Dry wall was delivered on Tuesday and has started installation today.
  • Paper and lath on the exterior are almost complete and we are expecting to pass Lath inspection mid next week.
  • Installation of all doors is complete.

Image 1 Image 2 Image 3 Image 4 Image 5 Image 6 Image 7 Image

Lot 1:

  • Rough electrical is in progress.
  • Rough HVAC IS 100% complte.
  • Rough plumbing is 100% complete.
  • Fire sprinklers inspection scheduled for 6/28.
  • All trades rough inspection is scheduled for 7/2 and 7/3.
  • Backyard patio concrete is poured.
  • Retaining wall footing poured.

Lot 2:

  • Framing has started.
  • Drainage, Waterproofing and Backfill has begun.

Lot 3:

  • In slab plumbing and in slab plumbing inspection were both completed.
  • Foundation contractors completed all the preparation for the slab. and passed structural and city inspections yesterday.
  • Middle level slab is poured as of 6/28 and is in progress.

Lot 4:

  • All trades inspection passed this week.
  • Insulation is completed and insulation inspection passed.
  • Ready for dry wall.
  • Exterior of the house has been papered.
  • Lath has been completed and waiting for inspection in order to start the scratch coat of stucco.

Img 1277 Img 3152 Img 3166 Img 4356 Img 7899

Lot 1: Soffits are completed, the 2nd story deck  framing is completed and all rough plumbing and rough HVAC is completed. Electrician is installing cans. Next week we will finish rough fire sprinklers. We will target to start pulling of electrical wires as well.

 

Lot 2: Drainage and Backfill of all retaining walls is complete. Framing material is delivered and will start in full swing on Monday.

 

Lot 3: Remaining piers for mid level house slab were poured, backfill was completed this week. Plumbers are working to complete in slab plumbing for mid level slab by tomorrow. We have in slab plumbing inspection on Monday and several tasks with goal to pour mid level slab by next Friday.

 

Lot 4: Fire sprinklers completed, Electrical wires are being completed throughout the house. We have all trades rough inspections scheduled for Monday and  Tuesday, followed by insulation installation and inspection towards the end of next week.


58265536197  996c4461 00fd 4464 9182 55034ad5a2da Img 8657 Img 8658 Img 8659 Img 8660 Img 8661 Img 8662 Img 8663 Img 8664 Img 8665 Img 8666 Img 8667 Img 8668 Img 8669 Img 8670 582826791 582826800 582826811

Lot 1: Rough HVAC and Rough Plumbing are complete. Team is working on Soffits and installing doors next week.

 

Lot 2: Foundation is 100% complete. Framing starting Monday.

 

Lot 3: Water proofing and backfill of retaining wall complete. Forms for upper slab underway. Next week, we will also pour 6 remaining piers and plumbers will complete in slab plumbing.

 

Lot 4: Soffits 95% complete, HVAC, Plumbing 100% complete. Fire sprinkler 80% complete. Next week we will complete installing all exterior doors, pulling in all electrical wires. Also target go pass all trades inspection.


Img 1844 Img 7310 Img 6025 Img 1322 Img 5655 Img 2649 Img 5187

Lot 1- This week, Framer completed items for waterproofing of exterior decks. Water proofing was completed for exterior decks. Most doors and windows with a few exceptions are now installed. Rough Plumbing is currently on its way. Next week rough HVAC will be completed and also creation of Soffits.

 

Lot 2 - In slab plumbing was completed and passed plumbing inspection on Wed. Foundation subcontractor is preparing for final slab and perimter wall pour scheduled for next Wed. Next week, we will begin Framing.

 

Lot 3 - Water proofing and backfilling for the lowest sections behind the retaining walls was completed. Water proofing for the middle section was also completed. The team is working on re-compacting dirt as well as backfilling. Next week, we are expecting to pour the piers for the mid level slab.

 

Lot 4 - Deck water proofing was completed, door pans were installed, soffits were created along with several minor framing changes. Next week, Rough Electrical and Rough Fire Sprinkler work will be completed.


Img 0706 Img 1386 Img 1468 Img 2747 Img 3126 Img 4141 Img 5014 Img 6584 Img 6735 Img 8261 Img 9690 Img 9538 Img 9690

Lot 1:

Most of the windows are installed. HVAC ducting is complete on 2nd floor.  Next week, Plumbing will be worked on before HVAC can be completed on 1st floor. 

 

Lot 2:

Drainage behind the wall is complete. Piers for top level living area as well as garage area  were poured, the walls for lower level is water proofed and backfilled.  Next week, plumber will do in slab work along side the preparation for slab for the 2nd floor living area. 

 

Lot 3:

Forms were stripped, drainage behind the wall is complete. Because of the rain, more dirt collapsed and was removed. Some sections of walls are water proofed. Next week, the entire wall will be water proofed and backfilled. 

 

Lot 4:

Rough HVAC is complete. Window installation is being worked on.  Next week Framer will install the soffits which will unblock the electrician for rough electrical work.


Img 1702 Img 1703 Img 1704 Img 1705 Img 1706 Img 1707

Lot 1: 

Rough frame is 100% complete and is ready for shear inspection

 

Lot 2: 

Retaining wall sub drain work is in progress

 

Lot 3: 

Retaining wall sub drain work is in progress

 

Lot 4: 

Rough plumbing is in progress

 


Img 1551 Img 1553 Img 1554 Img 1555 Img 1557 Img 1558 Img 1560 Img 1561 Img 1552

Lot 1:

Trusses have delivered and are being installed.

Plumber has started the plumbing layout.

 

Lot 2:

Concrete for the basement retaining wall is poured.

 

Lot 3:

Concrete for the basement retaining wall is poured.

 

Lot 4:

Trusses are installed.

Plumbing is in progress.

This lot is ready for Shear inspection on 5/20.

 

 


Img 1525 Img 1526 Img 1514 Img 1515 Img 1516 Img 1517
Lot 1:
- 2nd floor is framed and sheathed.
- Plumbing is to begin next week.
- HVAC layout has started.
 
Lot 2:
-Concrete contractors are installing the forms and finishing the retaining wall rebar in preparation for concrete pour.
 
Lot 3:
- Concrete contractors are installing the forms and finishing the retaining wall rebar in preparation for concrete pour.
 
Lot 4:
- Plumbing work has been started.
- HVAC layout has been started.
- Trusses have been delivered and are ready for install.

Img 1313 Img 1314 Img 1315 Img 1317 Img 1318 Img 1321 Img 1322 Img 1324 Img 1325

Extensive tree trimming is underway on the property which will open up the views and help with Sales & Marketing. We have a few engaged buyers with whom we are following up deligently.

Lot 1: Outside plywood and Second floor sub floor are 100% complete.We are working on standing walls for the 2nd floor.

Lot 2:The slab for the basement is 100% complete. Retaining walls are being worked on.

Lot 3: Basement slab is poured. Retainingg walls for the upper level are worked on.

Lot 4: 2nd floor walls are standing, plywoods will be worked on. 


Img 1244 Img 1245 Img 1246 Img 1247 Img 1248

Lot1: 1st Floor wall frames are 100% complete. Second Floor sub flooring is 100% complete.

Lot2: Basement wall rebar is 75% complete.

Lot3: Sub grade preparation and Matt slab rebar is being worked on.

Lot4: 2nd Floor sub flooring and wall layout is 100% complete.

 


Img 1218 Img 1219 Img 1220 Img 1221 Img 1222

Lot 1: First floor got framed. 2nd floor joists were installed.

Lot 2: Rebar for Retaining wall for lower floor is installed and will be ready for inspection next week.

Lot 3: Plumbing inspection passed at the basement level. Started putting forms for slab. Expect to pour the slab at basement level next week. 

Lot 4: Sub floor for 2nd floor started today.

 


Img 1148 Img 1149

On Lot 1 and Lot 4, we have poured the foundation and have started framing the homes. We are eager to be able to show the homes framed in order to best gain excitement from potential buyers. Lot 2 and Lot 3 foundation is making progress and we are scheduled to jump directly from framing 1 and 4. The cul-de-sac improvement work continues with the next large milestone being to start PG&E and water work for the new homes.


Img 2621 Img 2622 Img 2623 Img 2624 Img 2625 Img 2626 Img 2627

We are currently working on the subdivision improvements for the cul-de-sac. The large retaining wall and sewer work are complete and we will now begin working on the other utilities. The lot 1 foundation will be poured next week and we hope to also be able to pour the lot 4 piers. The rain has been a setback on the project, but we are hoping with a short break in the weather next week, we can make significant progress. 


57377816462  e24edb46 6632 4993 96bf 4a956bb9f0c0 57377822758  2f2fa9f4 2757 4d4f 85cc 3dae3c385af4 57377868033  015b58f1 c737 4a5e b0c2 84c14790c29d

On Aron Court, we are pushing ahead on the construction of the cul-de-sac with pier wholes drilled, rebar laid, and underground utilites continuing to make progress.  We are looking forward to completing the large retaining wall along the cul-de-sac next week, before proceeding forward with the sidewalk and adjacent reaining wall.  The piers for Lot 1's foundation are drilled, the inslab plumbing is complete, and we will be getting inspection next week in order to pour the first floor slab.


S 1.1 photo markup 1550008613070 S 1.1 photo markup 1550008609696 C 2.0 photo markup 1550008611865

We are well underway with the new cul-de-sac construction. We have constructed the large retaining wall that is on the uphill side of Talbyrn and have also completed the new sewer manhole construction. We will be working on installing utilities next for the cul-de-sac construction. The four homes are ready for foundation. We are currently working on lots number one and two, and then will be moving on to lots three and four. The foundation contractor, plumber, and framer will be working on the site simultaneously to make as much progress as possible.


S 1.1 photo markup C 2.0 photo markup 2 C 2.0 photo markup

We are waiting on the city of Belmont for the final signed paperwork in order for us to record the final parcel map with the county.  We are also finalizing the design specifications in order to complete the marketing materials, and will soon be bringing the lots to market one by one.  Please let us know if you know anyone who may be interested in buying or wants more information on any of the four homes.


Demolition is now complete and tree removal has finished. We are working closely with the City of Belmont to record our Final Parcel Map and Grading Permit so we can begin grading work.


The Final Map was approved by City Council this week. We are now working towards completing the requirements to pull the subdivision improvement plans and to record the Final Map with the County of San Mateo. We are actively researching cost savings related to the structure of the four homes and are working tightly with contractors to solidify bids.


Our City Council meeting is now scheduled for April 10th, at 7pm at the City of Belmont. This meeting is to officially record the final parcel map, approve the 3-way stop sign, adopt the name change to "Aron Court", and to vacate the Right of Way required to construct the new cul-de-sac. Demolition of the existing structure and tree's is scheduled for April 4th in prepartion to begin subdivision improvement work as soon we get City Council Approval.


The Subdivision Improvement Plans and Final Parcel Map have been approved by the City of Belmont. We are currently awaiting our Lot 1 and Lot 4 Building Permit comments. We will be resubmitting Lot 2 and Lot 3 this week. The City of Belmont has a grading moratorium until April 15th. We will be working with the City of Belmont, in collaboration with our contractors, to see what work, if any, we can proceed with prior to that date. 


The subdivision and site improvement plans are currently being reviewed by Public Works. Once the plans have been approved, we will begin the process of pulling the encroachment permits and getting our bonding in place for the work that is required in the public right of way. There is a grading moritorium in place until April which will greatly diminish the amount of work we are able to proceed with.


We have reviewed the Subdivision Improvement and Final Map plans with the plan checker to ensure all comments are addressed. We will be formally submitting this week. In addition, we will be resubmitting Lot 1 and Lot 4 building comments this week. Lot 2 and Lot 3 comments we are anticipating this week.


We have now compiled responses and documents to all of the comments as they relate to the Subdivision Improvement and Final Map. We will be attempting to set up a time next week to sit down with the plan checker to ensure we are on the same page with all items prior to formal submission. In addition, we are making good progress on addressing the Building Comments for Lot's 1 and 4. We should be ready to re-submit after the Holiday weekend. We are currently waiting to receive comments from Building Department on Lot's 2 and 3 as they are more complex and were submitted about one week later.


We have received comments from our submission to the Building Department for two of the four homes. We anticipate receiving comments on the other two submissions next week sometime. It will take us two weeks to turnaround re-submission to address those comments. As for the Final Map and the Improvement Plan, we are making progress and are working through the final requirements from the City of Belmont.


All four lots have now been submitted to the Building Department. We are also in communication with Contractors in order to collect proposals now that we have structural plans. We are also working to finalize our Subdivision Improvement Plans and Final Parcel Map. 


Two of the four homes are currently in their second week of Building Plan check. The other two homes Building Permit submission are prepared and are ready to submit this week. With with full package together, the objective will be to send it out to trades for bid over the coming weeks concurrent to plan review.


We have started our first construction activities with abatement on the existing structure's hazardous material. This is a predecessor to complete demolition. As for the permit submissions, two of the four homes were submitted to the Building Department on Friday of last week. We are working on complete the other two packages for submission to Building late this week or beginning of next. We are still ironing out the last of the comments for the Site Improvement and Final Parcel Map prior to formal resubmission.


We are nearing completion on two of the four building permit submissions. The reason for offset in timing has to do with the severe grade of the two remaining plan sets which adds to the complexity of the design. We are also spending a great deal of time preparing for the Site Improvement and Final Parcel Map packages. By working upfront with all parties, we are hoping to eliminate any possible comments prior to re-submitting and wasting costly time waiting for comments. Also, for anyone interested in watching the presentation to the Planning Commission that we had earlier this month, the video and minutes have been added to the following link: Planning Commission Meeting 09/05.


Now that we have planning commission approval, the next three large milestones will be to obtain our Site Development permit and Final Parcel Map, and submit to the Building Department for the individual homes. We are pushing to submit to Building in the next two weeks and are working with our consultants to wrap up the last of the comments remaining for the Site and Final Parcel Map.


We are working with the Civil Engineer on what we hope to be the last of the submittals to Belmont in order to obtain the Site Development permit. The Site Development work includes the construction of the new cul-de-sac, drive path, sidewalks, curbs, and utilities. Our goal will be to commence this work as soon as possible so we can jump into the construction of the 4 homes as soon as we have approval from Planning and Building Department. As mentioned in previous updates, the Planning Commissioning meeting is scheduled for tomorrow evening at the City of Belmont. Our goal for this meeting will be for the Commissioners to approve the project so we can move on to Building Department submission. I have attached some snapshots of our presentation for you to take a look at.


Screenshot 2017 09 04 15.16.20 Screenshot 2017 09 04 15.16.35 Screenshot 2017 09 04 15.16.57

Our Planning Commissioning date of 09/05 has been confirmed. For anyone, especially those who live in the Belmont Community, who would like to come out and show their support, it would be greatly appreciated! We are hoping to have our homes be the first on the agenda at 7pm. We have also been working closely with the Structural Engineer over the last week for design development of the structural plans.


We are currently working with the Design Team to finalize the Planning Commission presentation. We have a tentative date of September 5th for the hearing on all four homes in Belmont. We are working with the Structural Engineering team on a Design-Build approach to ensure that the proposed foundation designs are aligning with our budget. I have included a preview of some renderings that we will be using for presentation purposes.


2017 08 17  img 1 2017 08 17  img 2

We are awaiting confirmation for our public hearing date on all four homes. In the meantime, we are working with the design team in order to prepare the Building Permit package. 


We have received preliminary feedback from the Planning Department that two of the four lots have gained staff support. We will be working with the City of Belmont towards the beginning part of next week to address their concerns on the other two properties. Our goal will be to submit all four lots at the end of next week for what we hope will be the final submittal for Planning. Once that is complete, we will be put on the schedule for Planning Commission meeting.


We have resubmitted three of the homes to Planning. The fourth home, we have been going back and forth with Belmont to ensure that what we are re-submitting gains their support. The topography of the site makes conforming to their general guidelines quite difficult but our team is working diligently to make it happen. We just received the second round of comments on our Final Parcel Map and are expecting Site Improvement comments early next week. We are also concurrently working toward the demolition permit so we can hit the ground running once we have the Site Improvement permit.


Over the last few weeks, our primary focus has been to ensure that we are in the best shape possible going into our Planning Commission meetings. This includes completing neighborhood outreach as required as part of the public process and also having multiple meetings with the Planning Department to ensure we have their full support. We are also working to secure a demo permit and to begin Site Improvement work concurrent to Planning feedback.


We have received comments from Public Works and Planning on our first round submissions. All in all, they were relatively minor comments and our design team is currently working to implement the City of Belmont's comments. We are going to be resubmitting to Public Works documents early next week and Planning towards the end of next week.


We received Public Work comments last week and are working to address them. We are anticipating getting Planning comments over the next couple weeks for all four homes. 


Our consultants have been working hard in preparation to submit all four lots for Planning review next week. We have also begun speaking with contractors and vendors in order to value engineer the design.


For this project, we are using an Integrated Project Delivery approach- where all consultants are involved from the first design iteration in order to expedite the design process as much as possible. The tight coordination has been paying dividends in the form of delivering some very promising conceptual designs. We are working to finalize all building footprints and floor plans, while considering Structural and Civil conditions, prior to completing design development. We are hoping to formally submit to the planning department next week.


Screenshot 2017 02 24 15.56.39 Screenshot 2017 02 24 15.57.05 Screenshot 2017 02 24 15.57.17 Screenshot 2017 02 24 15.57.32 Screenshot 2017 02 24 15.57.57 Screenshot 2017 02 24 15.58.15 Screenshot 2017 02 24 15.58.44

Talbryn pre-construction is in full swing. We are preparing to submit the Final Parcel Map towards the end of this week. We are simultaneously working on the Architectural design, Arborist report, and Soils Engineering. We have included the conceptual design of the homes below, enjoy!

Talbryn Conceptual Renderings from Aron Developers LLC on Vimeo.


Our Civil Engineer has completed the first progress set for the subdivision improvement plans. Meanwhile, we are thoroughly vetting multiple Architecture and Structural Engineering firms in order to begin work on conceptual design of the four properties. 


Screen shot 2017 01 20 at 4.43.10 pm Screen shot 2017 01 20 at 4.44.06 pm Screen shot 2017 01 20 at 4.44.16 pm Screen shot 2017 01 20 at 4.45.25 pm