1. Construction- Lot 1 and 2: Construction work in in full swing on Lot 1. We have installed temporary Site infrastructure and have been done with Grading & staking on the site. We plan on starting foundation work as the shoring is about to finish in the next 2 days. The site work can be viewed here- Winding Way Los Altos August 29 2022

2. Finance- As a great progress, we secured financing on both the lots last month itself and we are working full speed ahead with the lender to keep the site funded at all times.


Whatsapp image 2022 09 14 at 1.22.06 am Whatsapp image 2022 09 14 at 1.22.07 am Whatsapp image 2022 09 14 at 1.22.08 am

1. Construction- Lot 1: Construction work in in full swing on Lot 1. We have installed temporary Site infrastructure and Grading . Shoring is in progress.

2. Building Permit-Lot 2: As a condition of Approval, the County required "Notice of Permit" for SS easement to be recorded which has been done this week. We are working with the permit technician to pay the final fees & pull the permit.

3. Finance- As a great progress, we have got approval on both the loans today and we working with teh lenders to do all the final underwriting work and anticipate to sign the loan documents and get the project fully funded in the next 2 weeks.


1.Building set- Lot 1: As a milestone, we have received the Building Permits as attached in this email. We already had the pre-construction Inspection meeting held at the site this week and look forward to break grounds next week.

Lot 2: The plans are now approved by the Building department and working with the county to pay the final fees & pull the permits.

3. Finance- Due to the financial volatality in the market the lender is taking a bit more time to approve and fund the loans. However, in terms of timelines we expect to close this by the end of the month. 


1. Construction- Lot 1: Construction work in in full swing on Lot 1. We have installed temporary Site infrastructure and Grading ./ Shoring is in progress.

2. Building Permit-Lot 2: As a condition of Approval, the County reuired "Notice of Permit" for SS easement to be recorded which has been done this week. We are working with the permit technician to pay the final fees & pull the permit.

3. Finance- Due to the financial volatality in the market the lender is taking a bit more time to approve and fund the loans. However, in terms of timelines we expect to close this by the end of the month. 


Winding way lot 02 view 03 Winding way lot 02 view 06

1.Building set- Lot 1: As a milestone, we have received the Building Permits as attached in this email. We already had the pre-construction Inspection meeting held at the site this week and look forward to break grounds next week.

Lot 2: The plans are now approved by the Building department and working with the county to pay the final fees & pull the permits.

3. Finance- Due to the financial volatality in the market the lender is taking a bit more time to approve and fund the loans. However, in terms of timelines we expect to close this by the end of the month. 

 


Winding way lot 02 view 01 Winding way lot 02 view 03 Whatsapp image 2022 07 25 at 8.16.44 pm Whatsapp image 2022 07 25 at 8.19.05 pm

1.Building set- Lot 1: As last updated, the Building plans are fully approved and we are expecting the stamped sets and permit early nect week.

Lot 2: The plans are currently under review and approval is expected by mid of this month.

2.Timelines- We are close to breaking grounds in coming 2 weeks starting the grading using previously approved Main house permit.

We can start following activities as per the current schedule -

1) Site clearance & Staking  - 07/20/2022 to 07/26/2022

2) Then proceed with shoring activity by -
a) Drilling & off hauling  - 07/29/2022 to 08/10/2022
b) Pouring & Curing of concrete - 08/10/2022 to 09/15/2022

3. Finance- As a signifigant progress we are about to close our construction financing on the project by early next week and hence break grounds. We expect the loan documents to be in for signing by early next week and close on it the same week itself.

This opportunity is very limited, as its an incredible chance to earn up to a 20% annualized return so be sure to Click here in order to  Invest Now and reserve your space in the offering. Please also feel free to reach out to us directly with any questions you have by responding to this email or giving us a call at (650) 567-4701.


1.Building set- Lot 1: As last updated, the Building plans are fully approved and we are expecting the stamped sets and permit early nect week.

Lot 2: The plans are currently under review and approval is expected by mid of this month.

2.Timelines- We are close to breaking grounds in coming 2 weeks starting the grading using previously approved Main house permit.

3. Finance- As a signifigant progress we are about to close our construction financing on the project by early next week and hence break grounds. We expect the loan documents to be in for signing by early next week and close on it the same week itself.

This opportunity is very limited, as its an incredible chance to earn up to a 20% annualized return so be sure to Click here in order to  Invest Now and reserve your space in the offering. Please also feel free to reach out to us directly with any questions you have by responding to this email or giving us a call at (650) 567-4701.


Winding way lot 02 view 04 Winding way lot 02 view 06

1.Building set- As a milestone Lot-2 plans are approved by the Building Department, and we look forward for the completion of balance reviews to pull the building permit.

For Lot-1, we have addressed all comments and compiled the set. The re-submission is currently blocked on Fire Flow test report which is delayed by the Water purveyor.

2.Timelines- We have closed most contracts on the projects and plan to break grounds soon with the previously approved Main House Drawings.

3. Finance- We are already working with the existing lender and also two new lenders on this project for the construction loan and are  looking to raise 1.5M Preferred equity for the soft costs and to begin construction. We are also awaiting on appraisal that was ordered by one of the lenders last week.

This opportunity is very limited, as its an incredible chance to earn up to a 20% annualized return so be sure to Click here in order to  Invest Now and reserve your space in the offering. Please also feel free to reach out to us directly with any questions you have by responding to this email or giving us a call at (650) 567-4701.


Winding way lot 02 view 01 Winding way lot 02 view 03

1.Building set- We expect the City comments to for both the lots by mid month. Since the last comments on the sets were not so intense, we expect approvals too.

2.Timelines- As the main house plans are already approved by the city we are planning to break grounds on the lot by early next month.

3. Finance- We are already working with the existing lender and also a new lender on this project for the construction loan and are also looking to raise 1.5M Preferred equity for the soft costs and to begin construction. 

This opportunity is very limited, as its an incredible chance to earn up to a 20% annualized return so be sure to Click here in order to  Invest Now and reserve your space in the offering. Please also feel free to reach out to us directly with any questions you have by responding to this email or giving us a call at (650) 567-4701.


Winding way lot 02 view 01 Winding way lot 02 view 07

1.Building set- We have resubmitted the building plans with the city this week based on the comments that we recieved after the addition of ADU on the lot. As the main house plans were already approved by the city we expect the building permits approval on the whole set by the next 4 weeks.

2.Timelines- As the main house plans are already approved by the city we are planning to break grounds on the lot by early next month.

3. Finance- We are already working with the existing lender on this project for the construction loan and are also looking to raise 1.5M Preferred equity for the soft costs and to begin construction. 

This opportunity is very limited, as its an incredible chance to earn up to a 20% annualized return so be sure to Click here in order to  Invest Now and reserve your space in the offering. Please also feel free to reach out to us directly with any questions you have by responding to this email or giving us a call at (650) 567-4701.