logo
logo
10800 Magdalena Rd, Los Altos Hills
about
Overview

The investment involves the acquisition of three adjacent residential lots in Los Altos Hills, CA, then rebuild and sale of three single family homes. The Sponsor will acquire the necessary permits, rebuild, and sell the first home within 16 month, and the remaining homes within 22 months.<br/><br/> The principals of the Project Sponsor have successfully built several homes in CA over the past decade. The Sponsor is in contract to purchase the property in late February. Accordingly, the primary objective of this investment is to (1) purchase the property, (2) complete the rebuild work upon closing of the transaction, and (2) sell the first home or cash investors out within 16 months.

about
Luxury Living

Aron Developers Inc. is a technology driven Real Estate Development company. We started in 2013 with the mission to revolutionize real estate development by using best in class software tools or build our own software tools in the four core areas of our business - acquisition/diligence, capital formation, operations and sales.


On Lot 2, we’ve completed all items put forth by planning and building departments and will be obtaining occupancy certificate this week while we prepare to close escrow with the buyers.  Lot 3 is on the market and we are conducting tours and holding regular open houses.  We have had several offers and have many disclosure packages out.  Tomorrow we will be price correcting to $5.65M and we will keep you posted on any and all activity.


On Lot 1, we received building final and occupancy last week. Since then, we have been working with the buyer to make sure the home is up to their satisfaction prior to closing escrow.

On Lot 2, we are approximately two weeks away from calling for final inspection. We hope to be able to close escrow soon after occupancy certificate.

On Lot 3, we have building final inspection scheduled for next week and are going to stage and bring the house as quickly as occupancy is obtained.


Unadjustednonraw thumb cdd Unadjustednonraw thumb ce1 Unadjustednonraw thumb ce5 Unadjustednonraw thumb ce0 Unadjustednonraw thumb ce4 Unadjustednonraw thumb cdf Unadjustednonraw thumb cd2 Unadjustednonraw thumb ce3 Unadjustednonraw thumb cde Unadjustednonraw thumb ce2 Unadjustednonraw thumb ce6
On Lot 1, we are currently pushing toward the close of escrow with the buyer. In order to close escrow, we need to obtain the occupancy certificate from the Town of Los Altos Hills. We are working closely with PG&E in order to expedite the gas and electric service as those are currently the largest outstanding items. 
 
For Lot 2, the interior is nearing completion with touch-ups and the finish trim installation commencing. We are preparing to begin the exterior landscaping and final inspections over the coming weeks. We are also working closely with PG&E on this lot to coordinate close of escrow with the buyer.
 
Finally, on Lot 3, staging is now complete on the interior and we are completing the exterior and interior punch-list items for photos as we prepare to bring the property to MLS. The goal is to bring the house to market by the end of the month. 

Bbgulyattqirwhp0ic8wfg Yi7pa2d8tocito5o4m7r7g T kdgdmytscoidtgx69gpq Vgkfxtlzrvcqttrihfebea I2abloehtlkqstex dkgig Scuutqr8t9umlomvdzyokq 4cefqiefq96trjhebh0aeq V5bcohtig5h5y9x3b99w Xjgij1srqfuibvakkzqsog Mqr2ify0snqjklbdjisviq 2kboh87cswmc9nlbozd0mw Cxjkk7putlkcca2h4spplq D4lw2whcs4krknbu iivcw Qpptakjxth6w8hrn9nbggw Uhoa8husqfqnnhz2nztg Psjs9ghdrzsh5iysmmsmkg J1qhif8ftdsby8y3khud7g Txxidn4xtfu3v1sx 1 bja

Lot 1 is now complete and is awaiting final inspection. We are waiting on PG&E to pull both gas and electric service, and for the Town of Los Altos Hills to issue occupancy certificate before being able to close escrow on the property. Lot 2 interior and exterior are approximately one month from completion and subsequent close of escrow. On Lot 3, we are completing the interior and exterior by April 11th, in hopes of being able to stage, list, and bring the house to market by middle of April.


Lot 1, the only things pending are utitlities and approval from Los Altos Hills.  Over the next few weeks we'll be completing punch list items on the interior, scheduling and coordinating final inspections, and wrapping up the last of the landscaping.

Lot 2 and lot 3, concrete driveway is now poured.  Interiors for both of the homes are approximately at the same stage.  We are pushing to have both interiors and exteriors complete by the end of this month.

Once again Lot 2 is in contract and will close upon occupancy certificate.  For Lot 3, we have a stageing date at the end of this month in order to bring the property to market.

On all three lots, PG&E remains the longpole in getting occupancy cerrtificate, and we are doing evertyhing we can to expidite the process.


10888 magdalena ave los altos large 002 10 front closeup at dusk 1500x1000 72dpi Img 2744 Img 2745 Img 2746 Img 2748 Img 2750 Img 2751 Img 2753 Img 2754 Img 2755 Img 2756 Img 2758 Img 2759 Img 2760 Img 2761 Img 2762 Img 2764 Img 2765 Img 2766 Img 2773 Img 2777

On the three homes, the site retaining walls are making good progress. The utilties have not yet been pulled. We are currently waiting on inspections from PG&E. On Lot 1, the interior is complete. On Lot 2 and Lot 3, the cabinet installation, flooring and trim are done. The stairs, handrail, countertops and finish trim on the electrical and plumbing are to follow.


Img 8599 Img 8598 Img 8602 Img 8604 Img 8605 Img 8607 Img 8608 Img 8610 Img 8612 Img 8617

On Lot 1, the interior is now complete with the exception of the interior staircase and railings. On Lot 2 and Lot 3, the interior trim is nearly complete, exterior facade, tile and hardwood are making progress. On the exterior, the driveway retaining wall piers have been inspected and we are working to schedule concrete delivery. The utilities are about 75% complete and we will be having our second PG&E inspections this coming week.


2074a020 933d 403d aff4 6a50e4262134 B2bc3ad0 ad4c 4be6 8b78 ec6d7d6875b9 53af9098 ea88 4e8b a984 b4880e7d9660 1a02df8d 6c96 4cb5 b1ba 2615507ce181 008a65fb f93d 467d 89d6 420d6e26f4af 64edbdf4 f854 46a7 8869 e1910f91ee73 Ec0b5186 91f5 4a54 9bbe 2f9355b29998 46ee3d8d 7148 4739 9a85 72db8a6bdc56 6220b9ab f84d 40f5 b577 77aa2641f349 Eb21671c 6afe 42a1 bc2b 118d452cafd0 6f713cb6 ecec 449d a17e 162b4ae82de2

On Lot 1, the interior is nearly complete with baseboard being installed and touch-up being wrapped up. Lot's 2 and 3 remain a couple months behind Lot 1. The cabinets are now installed, flooring is being delivered, and paint is complete. Regarding the site work, the driveway retaining walls are making progress with piers now drilled and reinforcement being delivered. The utilities are about 50% complete and we will be having our first PG&E inspections this coming week.


Img 8513 Img 8514 Img 8515 Img 8506 Img 8507 Img 8508 Img 8509 Img 8512

On Lot 1, the interior is nearing completion. Flooring, tile, and fixtures have all been installed. We will be completing baseboard installation and touchups over the coming weeks. On the exterior, the driveway retaining walls are underway and utility work is making connections in the street. On Lot 2, the interior cabinets are installed, tile is making progress, and flooring will be the next item to be installed. On Lot 3, interior paint is complete, trim is installed, and cabinet installation is about to begin. On the exterior, retaining walls for the shared driveway is making progress and utility work is underway.


Img 8489 Img 8490 Img 8491 Img 8492 Img 8493 Img 8494 Img 8495 Img 8496

On Lot 1, the cabinet island has now been stained and flooring material is being stocked to acclimate. The flooring installation will start next week. Lot 2 interior paint is almost complete upstairs, tile is delivered, and cabinet installation is nearing completion. The scaffolding is erected and we are working on lath as we prepare for stucco. Lot 3 priming of ceilings and walls are almost complete. The interior trim is also making progress. The exterior is being prepped for the last coat of stucco. For the site work on the exterior, the drainage system is being worked on and will be followed closely by the utilities.


Img 8412 Img 8414 Img 8415 Img 8416 Img 8420

Lot 1 fixtures are now installed and the home is being prepped for flooring installation. Lot 2 interior paint is underway and cabinets have delivered and will be installed over the coming week. We will also be starting to scaffold the exterior of the house as we prepare to complete exterior finishes. Lot 3 drywall is nearly complete and priming of walls will commence shortly.


2017 10 12 17.06.07 2017 10 12 17.06.36 2017 10 12 17.07.39 2017 10 12 17.10.35 2017 10 12 17.14.01 2017 10 12 17.15.33 2017 10 12 17.16.30 2017 10 12 17.16.53

Lot 1 continues to move along quickly. Countertops are installed, backsplashes are complete, and painting is nearing completion. Lot 2 priming is underway, bathrooms are being prepped for tile, and drainage is being completed on the exterior so we can scaffold the home and begin stucco. Lot 3 drywall work is progressing, the roof material is loaded, and the exterior patio is ready to be poured. On the exterior of the 3 homes, we have completed all grading and we are currently working on the drainage for the site.


Img 8352 Img 8354 Img 8357 Img 8359 Img 8361 Img 8362 Img 8363

Magdalena Lot 1 continues to progress and is the furthest along of the three homes. The interior tile is done with the exception of the backsplashes, interior paint is progressing and will be closely followed by the electrician to set fixtures. Lot 2 drywall is now complete and the painter is working to prime the house. We are working to get cabinet delivery scheduled and begin tile work. On Lot 3, the roof has been loaded with the tile, the back patio is being prepared to be poured, and drywall work is coming along.

The site work is also making progress as the grading contractor is working his way out of the site, starting with Lot 1.


2017 09 22 14.04.33 2017 09 22 14.06.24 2017 09 22 14.07.13 2017 09 22 14.11.00 2017 09 22 14.14.19 2017 09 22 14.18.44 2017 09 22 14.20.00

On Magdalena Lot 1 exterior, painting is nearing completion, roofing is done and gutters are being installed. On the interior, tile is complete in the bathrooms, trim is almost done, and the painter is progressing nicely. On Lot 2, drywall finishing is completing, interior doors are being installed and we are preparing for tile. On Lot 3, the stucco first coat is done, drywall is being taped, and the roof is being prepped for installation. In conjunction to the homes, we are also working to schedule items for the site work (utilities, drainage, landscaping, etc.). We are hoping to work on that in parallel to the home construction completing.


2017 09 15 13.41.28 2017 09 15 13.41.50 2017 09 15 13.42.00 2017 09 15 13.42.02 2017 09 15 13.43.17 2017 09 15 13.44.09 2017 09 15 13.44.57 2017 09 15 13.47.51 2017 09 15 13.48.45 2017 09 15 13.49.25 2017 09 15 13.49.29

Drywall is progressing on both Lot 2 and Lot 3. We are also working on exterior lath and scaffolding in preparation to begin stucco. On Lot 1, cabinets were delivered and installed, finish coat of stucco is done and we are working on tile and paint on the interior.


Img 8147 Img 8150 Img 8151 Img 8152 Img 8154 Img 8155 Img 8161

Magdalena Lot 1 priming just completed and we will begin applying color to the interior walls next week. We will also start installing interior door and window trim, and door installation. On the exterior, we are on our last coat of stucco and will soon start painting. Magdalena Lot 2 drywall hanging is complete and they will begin tape and finishing next week. Magdalena Lot 3 insulation is complete and drywall has been stockpiled. We will begin hanging drywall next week.


Img 8104 Img 8105 Img 8106 Img 8107 Img 8108 Img 8109 Img 8110 Img 8111 Img 8112 Img 8113 Img 8114

Magdalena Lot 1 drywall is finished. We will be beginning paint next week and will be starting our last layer of stucco on the exterior next week as well. Magdalena Lot 2 drywall has just started. We will be continuing drywall over the next couple weeks and will be working on lath and stucco as well. Magdalena Lot 3 drywall is about to begin. We will finish up the last of the insulation and then beginning drywall and exterior lath and stucco. 

We are also working to finish up the last of the property website pages which can be found here:

https://www.arondevelopers.com/properties/10800-magdalena

https://www.arondevelopers.com/properties/10880-magdalena

https://www.arondevelopers.com/properties/10888-magdalena

Please feel free to share with family and friends.


Img 8075 Img 8076 Img 8077 Img 8078 Img 8081 Img 8082 Img 8083

Magdalena homes are coming along nicely. On Lot 1, we are finishing drywall and working on the first layer of stucco. On Lot 2, all-trades inspection has passed, roofing is complete, and the home is insulated. We will be working on drywall and lath next week. On Lot 3, we will begin insulation next week, preparing the roof for tile, followed closely by drywall.


Img 8032 Img 8033 Img 8038 Img 8041 Img 8042 Img 8043

On Lot 1, we are currently awaiting all trades inspection prior to proceeding with drywall. On the exterior, we are ready to stucco but are waiting until the drywall is hung to prevent cracking. On Lot 2, plumbing and electrical are complete. HVAC is underway and fire sprinkler will be starting next week. On Lot 3, electrical and plumbing are underway. On all three lots, we are working with the City and PG&E to complete utility approval process. We are also working with the listing agent on a go-to-market strategy for pre-selling the three homes.


Img 0970 Img 0971 Img 0972 Img 0974

On Lot 1, we have completed all rough in and are ready for all trades inspection for next week. Roofing is almost done and we are getting ready to erect scaffolding in preparation for stucco. On Lot 2, windows are about 50% installed and we are roughing in electrical and plumbing. On Lot 3, we passed shear inspection today, and are preparing to install windows and begin rough-in.  


Img 0946 Img 0947 Img 0949 Img 0950 Img 0951 Img 0953 Img 0955

Magdalena Lot 1 framing is now complete, windows and doors have been installed, mechanical, electrical and plumbing rough-in is nearing completion, and the roofing material is loaded in preparation to begin the installation. Lot 2 shear inspection passed today and we will begin window and door installation next week. Lot 2 framing was slightly delayed as the team made the decision to swap the master bedroom "wing" with the guest "wing" of the house in order to best optimize for the breathtaking views. Lot 3 framing is going to be the last to be complete due to the complex circular roof framing design. 


Img 0902 Img 0903 Img 0904 Img 0906

Lot 1 framing has now surpassed the other two lots. They are currently sheathing the roof with preparation for framing inspection next week. Lot 2 roof trusses were delivered today and will be installed next week. Lot 3 circular entry is providing a challenge to the framing crew but they will be finishing the second story wall framing next week and will then start roof framing.


Img 0873 Img 0876 Img 0882 Img 0884 Img 0888 Img 0889

Framing is in full swing on all three lots. Lot 1 slab and retaining wall are now poured and the first-floor framing is nearly complete. We are currently placing the second-floor joists and will sheathing and standing walls for the second floor starting next week. Lot 2 second-floor framing is complete and we are now just waiting on the pre-fabricated roof trusses to arrive before wrapping up framing. On Lot 3, the floor joists have been replaced per manufacturer recommendations and the first-floor walls are nearly complete.


Img 0813 Img 0832 Img 0842 Img 0837 Img 0839 Img 0840 Img 0841 Img 0834 Img 0836

On Lot 1, all concrete piers have been poured. The plumbing and waterproofing are complete for the slab and the concrete crew is currently forming rebar in hopes of being able to pour next week. On Lot 2, the first-floor wall framing is almost complete. On Lot 3, due to extended moisture exposure, the floor joists are having to be completely replaced. This is due to the manufacturer raising concern over the expansion of the plywood. While a difficult decision to backtrack and replace, we always try to deliver the best quality end product.


Img 0776 Img 0777 Img 0780 Img 0781 Img 0783 Img 0784

On Lot 1, we have all the piers prepared to be poured. In order to fight the rain, we brought a vacuum truck to site in order to pump the water that has accumulated over the course of the last few storms. Rebar cages have been placed into the 15' piers and are ready for concrete on Monday. The next step will be the retaining walls, and then the slab. On Lot 2, we are almost complete will all bottom plate detail. Starting tomorrow, we will begin wall framing. On Lot 3, we just completed pumping all the rain water out of the crawlspace. On Monday we will pour the rat slab followed closely by the framing.


Img 0767 Img 0768 Img 0755 Img 0756 Img 0757 Img 0758 Img 0759 Img 0760

On Lot 1, the waterproofing and backfill of the garage retaining walls are now complete. We have started drilling the piers for the first-floor slab and are making a push to try to complete pouring by this week. For Lot 2, we have completed pouring the first-floor retaining walls and are ready to now begin framing. On Lot 3, we are completing the crawlspace preparation prior to completing subfloor and framing. 


Img 0653 Img 0657 Img 0660 Img 0652

We have poured all of the garage retaining walls on Lot 1 and the driveway is operational. We will begin pier drilling for the first floor as soon as the pad has sufficiently dried out. On Lot 2, the slab foundation is complete and we will begin forming the retaining walls next week. Lot 3 floor framing is complete and plumbing is underway. As soon as underfloor rough-in is complete, we will sheath the first floor.


Img 0620 Img 0621 Img 0622 Img 0623 Img 0624 Img 0625

Magdalena property is progressing very nicely. On Lot 3 we have completed floor framing and are preparing for underfloor plumbing and mechanical. For Lot 2, we have completed exterior formwork and have passed subgrade plumbing inspection. We have backfilled and are doing subgrade preparation for our slab foundation. Lot 1 slab has been poured and the team is currently forming the garage/basement level retaining walls.


Img 0602 Img 0604 Img 0605 Img 0617 Img 0618 Img 0619

Magdalena property is progressing very nicely. On Lot 3 we have completed floor framing and are preparing for underfloor plumbing and mechanical. For Lot 2, we have completed exterior formwork and have passed subgrade plumbing inspection. We have backfilled and are doing subgrade preparation for our slab foundation. Lot 1 slab has been poured and the team is currently forming the garage/basement level retaining walls.


Img 0595 Img 0589 Img 0590 Img 0591 7 00000 %282%29 7 00001 %281%29 6 00001 %282%29

All three lots are progressing quickly. The rain has provided a little bit of a challenge, but we are actively pushing forward. For Lot 1, the garage level is almost complete and the team is currently preparing the subgrade on the first level. On Lot 2, we have poured approximately half of the exterior footings. On Lot 3, all piers have been poured and we are currently forming the grade beams.


Screenshot 2016 11 23 11.09.14 Screenshot 2016 11 23 11.10.02 Screenshot 2016 11 23 11.13.04 Screenshot 2016 11 23 11.14.46
We are making great progress on all three lots at Magdalena. For Lot 1, we completed drilling the piers are the garage level and are currently working on forming the slab. As soon as the garage has been poured, we will move up to the first-floor foundation. On Lot 3, the pier drilling is almost complete. Simultaneous to the pier's being drilled, we are forming the rebar cages to drop them in place. Lastly, on Lot 2, we just completed layout for the foundation. We will begin excavating for the footings next week.
Img 0567 Img 0573 Img 0574 Img 0575
Lot 2 and Lot 3 have both been staked by our surveyors in preparation to begin foundation work. We are currently off-hauling all the excess soil that are required to construct the homes. We will continue that trucking work into the better half of next week. When the off-hauling is complete, our survey team will move down to Lot 1 to stake and prep for foundation work to begin there.
Img 0524 Img 0526 Img 0527 Img 0529
We are progressing nicely at Magdalena. All three homes have significant grading work complete. Both Lot 1 and Lot 3 are to pad elevation and are ready for foundation work to begin. On Lot 2, we still have minor grading work to be complete.
10 4 2016 %281%29 10 4 2016 1 10 4 2016 2 10 4 2016 3 10 4 2016 4 10 4 2016 5 10 4 2016
We had previously received building permits on Lot 1 and Lot 3. For Lot 2, we submitted updated plans to address the 1st round building plan check comments. Demolition and grading are in full swing. The entire crew is working hard to finish by grading moratorium date which is October 15th.
Img 7295 Img 7296 Img 7297 Img 7298 Img 7299
Tree protection, tree removal, and mobilization are now complete on all lots. Lot 2 appeal period has expired and we have submitted to the outside building plan checker and expedited the review in order to get approval as soon as possible. We will be working on demolition next week and then moving into grading for Lot 1. Lot 3 and Lot 2 will follow.
Lot 1 and Lot 3 have received formal approval from the Town of Los Altos Hills. We will begin site mobilization next week followed closely by demolition. For Lot 2, we have submitted all documents required in preparation for building plan submission. We are continuing to work on structural plans so we can submit as soon as our appeal period has expired.
Mag1 Mag2 Mag3
We have received outside plan check approval for Lot 1 and Lot 3. The plans have been routed to the Town of Los Altos Hills for formal issuance and approval. We anticipating getting Building Permits next week and are preparing for demolition and earthwork. For Lot 2, in a great team effort, we received unanimous approval from the Planning Commissioners meeting we had on Tuesday of this week! There will be a 22 day appeal period. We will be preparing all of our submission documents in the meantime.
We have resubmitted Lot 1 and Lot 3 to Los Altos Hills incorporating their comments. For Lot 2, we are preparing for the Planning Commissioning meeting which will take place August 23rd.

We have created a 3D aerial model for the present, which can be viewed here:


We have received first round comments from the Building Department for Lot 1 and Lot 3. We are currently working to address comments for resubmission. Our plan is to resubmit early next week. For Lot 2, we are preparing for the Planning Commissioning meeting which will take place August 23rd. We have begun preparing our submission to the Building Department in anticipation of Planning Commissioning approval. A full 3d rendering of Lot 2 has been completed for presentation purposes.
Floored scene screenshot2016 08 12t23 15 39.145z Floored scene screenshot2016 08 12t23 18 22.989z Floored scene screenshot2016 08 12t23 18 30.547z Floored scene screenshot2016 08 12t23 18 46.824z
We have submitted Lot 1 and Lot 3 to the Building Department for approval. Over the next few weeks, we will be making sure to satisfy the Conditions of Approval in preparation to be able to pull the permit as soon as the plans are approved. For Lot 2, we are preparing for the Planning Commissioning meeting which will take place August 23rd. We have begun preparing our submission to the Building Department in anticipation of Planning Commissioning approval.
Lot 3 appeal period has expired and we are preparing a revision in response to Civil Engineering prior to complete submission. Lot 1 we have received Civil Engineering approval and are working closely with the other departments to make sure we are submitting exactly what they wish to see. For Lot 3, we are currently working on a 3d model in preparation for the Planning Commissioning meeting. Our team has also begun the process of exploring interior design on all three of the homes.
Lot 1 appeal process has expired as of yesterday and we are currently wrapping up all submission documentation to the Building Department. Lot 3 appeal period will expire next week. For both Lot 1 and Lot 3, we plan to submit next week to start the clock on Building Permit issuance. Lot 2 Planning Commission meeting is scheduled for the end of August and we are currently preparing a thorough presentation for the board.
We had Fast Track hearing for Lot 1 June 14 and Lot 3 June 21. In a great team effort, we received approval for both Lot 1 and Lot 3 and are currently compiling all documentation for submittal to Building Department. There is a 22 day appeal process that we have to wait for until submitting. We are planning to submit as soon as that 22 day appeal period expires. Lot 2 is not far behind. We have completed all recommendations from the Planning Department and are fully prepared for Planning Commissioning meeting which we are waiting to hear a confirmed date for.
Lot 2 story pole staking is completed. For Lot 1 and 3, we are waiting for fast tracking hearing in the up-coming two weeks. Structural engineering is in progress for Lot 1. Construction drawing is in progress for Lot 3.
6 6 2016 %282%29 6 6 2016 6 6 2016 %281%29 6 6 2016 %283%29
Fast track hearing for Lot 1 is scheduled for June 14, and we expect it to be scheduled for Lot 3 for June 21. Construction drawings and structural engineering are being done in parallel. We are planning on recording the necessary easements within the next two weeks. Story poles are installed on Lot 1 and Lot 3 today. We met with four neighbors and received two supporting letters from them. We are meeting with the fifth neighbor next week, in preparation for the hearing.
We have completed story pole staking for Lot 1. For Lot 2, we resubmitted plans based on Open Space Committee's recommendation. Meanwhile, we have signed contractor with interior designer who will begin working on Lot 1.
We submitted feedback for Lot 1 and Lot 3 and will expect to receive notice for fast-track hearing in three weeks. For Lot 2, we submitted a redesign to mitigate the number of trees displaced (from 12 to 3), based on information provided by the city. By doing this, the chance of this project having to go through planning commission is greatly reduced.
We have received comments on Lot 1 and are expecting to turn it around next week. At that point, we should be scheduled for fast-track hearing in May. For Lot 2, we will be submitting revised location per city feedback by early next week. For Lot 3, we are expecting to receive feedback by early next week also.
We are getting ready to submit for building permit for Lot 3 - waiting for planning department's final approval. For Lot 2, we anticipated going to planning commission for abandoning original driveway, but it turned out that we don't need to do that. However, we have to change the location of the house in order to preserve more trees than originally proposed. For Lot 1, we are still waiting for comments from planning department.
We received comments on Lot 1 and Lot 2. We have submitted revised plans based on comments on Lot 1 and Lot 3, and will submit the same for Lot 2 early next week.
We closed escrow on Monday, March 14. New address assignment for all three lots have been approved. We have received comments from Town of Los Altos Hills for Lot 3. All comments were minor and we are planning on resubmission early next week.
We have signed loan docs on Tuesday, March 8th. Tentative close of escrow is this coming Friday. All tenants have moved out - one of the contingencies. We are waiting on comments from Town of Los Altos Hills. Below are plans and front elevation for Lot 1.
Magdalena lot 1 floor plan 2 Magdalena lot 1 floor plan 1 Magdalena lot 1 front elevation
We have submitted Lot 1 last Friday to Los Altos Hills planning department. That means now all 3 lots have been submitted to planning.
We have submitted to planning department for 2 of the 3 lots. We are working on submitting the 3rd lot to planning department by next week. Close of purchase escrow is scheduled to be 2/26/2016. Additionally, we have secured $1.5M in preferred equity to fund this project. This is in addition to equity capital provided by Aron Capital Partners LP fund.