06/28/2020 Fencing installed. USA marking & water spicket installation done. Asbestos removal planned on 2nd & 3rd July 2020. Demolition planned on 5th,6th & 7th July 2020. Job card received. Power pole permit received. Application for new power & gas connection is done.